BOOZ ALLEN HAMILTON INC

Federal contract award, Booz Allen Hamilton, $44,612,123

Key CONT_AWD_0007_9700_W56KGU15D0004_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 400 days before this system saw it. One version on record.

Cite this row

On this site https://evidence.ourrevolution.media/filings/booz-allen-hamilton/CONT_AWD_0007_9700_W56KGU15D0004_9700
At the source https://www.usaspending.gov/award/CONT_AWD_0007_9700_W56KGU15D0004_9700
Observed 2026-09-05, version 1, retrieved 2026-09-05T00:51:49Z
Content hash 3e16dfa7939a4e973de267905627602f3a3eae9ce0c3a28548249889d15b1f34

The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.

Versions

VersionAmountChangeOccurredPublishedRetrievedHow it arrivedContent hash
1
current
$44,612,123first versionApril 26, 2018August 1, 20252026-09-05T00:51:49Zhistorical sweep3e16dfa7939a

Archived copy

None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.

What the amount is made of

59 recorded actions, so the amount is the award's current total across all of them. 48 of them obligated money. Measured 2026-10-18, when USAspending reported a total obligation of $44,612,123.

Action dateModificationTypeObligatedDescription as recorded
August 1, 202558FUNDING ONLY ACTION−$132,480THIS TASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE OPERATION, PROGRAM MANAGEMENT, TECHNICAL, ENGINEERING, INTEGRATION, PROTOTYPE DEVELOPMENT AND FABRICATION, AND PROGRAM SUPPORT.
February 7, 202557FUNDING ONLY ACTION−$1,310,802THIS TASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE OPERATIONAL, PROGRAM MANAGEMENT, TECHNICAL, ENGINEERING, INTEGRATION, PROTOTYPE DEVELOPMENT AND FABRICATION, AND PROGRAM SUPPORT.
November 27, 202356FUNDING ONLY ACTION−$227,205THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS.
May 3, 202355FUNDING ONLY ACTION−$21,803THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS.
February 28, 202354FUNDING ONLY ACTION−$12,327THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS
February 7, 202353FUNDING ONLY ACTION−$3,647THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS.
February 28, 202252FUNDING ONLY ACTION−$40,000DE-OBLIGATION -$40.000.00
December 13, 202151FUNDING ONLY ACTION−$28,097DE-OBLIGATION OF FUNDS
August 4, 202150FUNDING ONLY ACTION−$332,677DEOBLIGATION
June 9, 202149FUNDING ONLY ACTION−$795,768DE-OBLIGATION
May 14, 202148FUNDING ONLY ACTIONno moneyTRANSFER GFP
March 25, 202147OTHER ADMINISTRATIVE ACTIONno moneyTRANSFER OF GFP
March 5, 202146FUNDING ONLY ACTION+$776,708FUNDING
February 5, 202145FUNDING ONLY ACTIONno moneyRE-ALIGNMENT
January 14, 202144FUNDING ONLY ACTION−$551,140DE-OBLIGATION
December 21, 202043FUNDING ONLY ACTION+$184,000LABOR FUNDING
December 10, 202042FUNDING ONLY ACTIONno moneyPOSSIBLE TO RE-ALIGN SOME TRAVEL DOLLARS TO LABOR, AS WELL AS POSSIBLY EXTEND THE POP.
November 25, 202041FUNDING ONLY ACTION+$300,376FUNDING LABOR AND TRAVEL
November 19, 202040FUNDING ONLY ACTION−$2,602DE-OBLIGATE TRAVEL FUNDS
November 3, 202039FUNDING ONLY ACTION+$8,831889 COMPLIANCE AND INCREMENTAL FUNDING.
September 29, 202038FUNDING ONLY ACTION+$160,000THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $160,000.00.
September 28, 202037FUNDING ONLY ACTION+$3,937,500THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $3,937,500.00.
September 24, 202036FUNDING ONLY ACTION−$355,408ULO DEOB
September 15, 202035FUNDING ONLY ACTION+$329,882THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $329,881.56.
September 1, 202034OTHER ADMINISTRATIVE ACTIONno moneyTHE PURPOSE OF THIS MODIFICATION IS TO TRANSFER GOVERNMENT FURNISHED PROPERTY ONTO THIS CONTRACT.
July 30, 202033FUNDING ONLY ACTION+$2,289,613FUNDING FOR LABOR, TRAVEL AND MATERIAL
July 24, 202032OTHER ADMINISTRATIVE ACTIONno moneyMODIFICATION TO TRANSFER GFP FROM NAPS (W56KGU15D0004 0006)
June 30, 202031CHANGE ORDER+$2,239,800THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $2,254,800.00 AND EXTEND SLIN POP DUE TO COVID.
June 18, 202030FUNDING ONLY ACTION+$437,860THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT $437,860.00.
May 1, 202029FUNDING ONLY ACTION+$6,701,821FUNDING
April 29, 202028EXERCISE AN OPTION+$150,000THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 2 WITH A PERIOD OF PERFORMANCE FROM 01 MAY 2020 - 30 APRIL 2021.
March 19, 202027FUNDING ONLY ACTION+$330,600FUNDING MOD
March 17, 202026FUNDING ONLY ACTION+$1,960,160FUNDING ONLY
February 13, 202025FUNDING ONLY ACTION+$944,496THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $944,496.00.
February 3, 202024FUNDING ONLY ACTION+$471,752THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $471,752.00 ONTO THIS CONTRACT.
January 16, 202023OTHER ADMINISTRATIVE ACTION+$270,073THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $270,073.32.
November 20, 201922FUNDING ONLY ACTION+$190,000THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $190,000.00 ONTO THIS CONTRACT.
November 19, 201921OTHER ADMINISTRATIVE ACTIONno moneyTHE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING IN THE AMOUNT OF $163,726.00 FROM LABOR TO TRAVEL AND MATERIAL.
September 25, 201920SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyEXTEND POP TO 15 OCT 2019
September 18, 201919FUNDING ONLY ACTION+$220,787TO PROVIDE INCREMENTAL FUNDING.
September 16, 201918FUNDING ONLY ACTION+$906,582INCREMENTAL FUNDING RDTE.
August 27, 201917FUNDING ONLY ACTION+$625,549ENGINEERING SUPPORT SERVICES
July 24, 201916OTHER ADMINISTRATIVE ACTION+$2,197,935THE PURPOSE OF THIS CONTRACT IS TO INCORPORATE FUNDING IN THE AMOUNT OF $2,197,934.95.
June 28, 201915OTHER ADMINISTRATIVE ACTIONno moneyTHE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE PERIOD OF PERFORMANCE FOR OPTION YEAR 1 SLINS.
June 17, 201914FUNDING ONLY ACTION+$1,633,406THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $1,633,405.66.
May 1, 201913EXERCISE AN OPTION+$5,920,191THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $5,920,190.84, EXERCISE OPTION PERIOD 1 WITH A PERIOD OF PERFORMANCE FROM 01 MAY 2019 TO 30 APRIL 2020, AND TO DEOBLIGATE FUNDING FROM THE BASE PERIOD IN THE AMOUNT OF $489,325.00.
March 29, 201912FUNDING ONLY ACTION+$2,471,492THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $2,471,491.84
February 28, 201911FUNDING ONLY ACTION+$2,487,319THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $2,632,106.46.
January 25, 201910FUNDING ONLY ACTION+$1,136,752THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $1,136,751.51.
January 3, 20199OTHER ADMINISTRATIVE ACTIONno moneyTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE SOFA CLAUSE TO THIS TASK ORDER.
November 21, 20188FUNDING ONLY ACTION+$21,380THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $21,380.00.
November 19, 20187OTHER ADMINISTRATIVE ACTION+$270,713THE PURPOSE OF THIS MODIFICATION IS TO REALIGN $153,000.00 FROM SLIN 0005AD TO SLIN 0009AF AND TO INCORPORATE FUNDING IN THE AMOUNT OF $270,713.00.
October 5, 20186OTHER ADMINISTRATIVE ACTIONno moneyTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE SUBCONTRACTORS.
September 26, 20185FUNDING ONLY ACTION+$3,938,395THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $3,938,394.60.
September 11, 20184FUNDING ONLY ACTION+$148,405THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $148,405.14.
August 22, 20183OTHER ADMINISTRATIVE ACTION+$3,478,164THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $413,867.00 AND TO DEOBLIGATE FUNDING IN THE AMOUNT OF $-105,740.30 FROM SLIN 0002AA.
July 9, 20182FUNDING ONLY ACTION+$672,798THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $672,798.00.
May 29, 20181FUNDING ONLY ACTION+$507,000THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $507,000.00.
April 26, 2018basenot on file+$105,740THE PURPOSE OF THE CONTRACT IS TO ESTABLISH TASK ORDER 007 MATURATION OF AIRCRAFT AND VEHICLE PROTECTION SYSTEMS BASED ON ENGINEERING AND NOVEL TECHNIQUES(MAVEN)AND INCORPORATE FUNDING IN THE AMOUNT OF $105,740.30.