BOOZ ALLEN HAMILTON ENGINEERING SERVICES, LLC
Federal contract award, Booz Allen Hamilton, $8,561,088
Key CONT_AWD_0223_9700_DAAB0703DB006_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 306 days before this system saw it. One version on record.
Cite this row
ed94f2a9798a1b6362df915eecfad0f956d70cbe4b8cda3417da6ab0b5a96a13The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $8,561,088 | first version | July 5, 2007 | November 3, 2025 | 2026-09-05T00:52:36Z | historical sweep | ed94f2a9798a |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
36 recorded actions, so the amount is the award's current total across all of them. 21 of them obligated money. Measured 2026-10-16, when USAspending reported a total obligation of $8,561,088.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| October 15, 2025 | 1B | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | CLOSEOUT ISSUED PURSUANT TO DFARS 204-804(3)(I) SECTION 820 OF NDAA |
| August 24, 2016 | 1A | OTHER ADMINISTRATIVE ACTION | −$2,332 | NEEW TASK ORDER FOR C/KC-135 SYSTEM SUSTAINMENT AND SUPPORT |
| April 1, 2015 | 33 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO TRANSFER PURCHASING OFFICE RESPONSIBILITY FROM W15P7T (ACC-APG DIVISION B) TO W56JSR (ACC-APG DIVISION E). |
| July 16, 2009 | 32 | CHANGE ORDER | no money | INCORPORATING DISPOSITION INSTRUCTIONS FOR EXCESS MATERIAL ON ENGINEERING ASSIGNMENT NO. 8 |
| June 3, 2009 | 31 | CHANGE ORDER | no money | EXTENDING PERIOD OF PERFORMANCE FOR SLIN 0007AZ AS A RESULT OF INCORPORATING A REVISED ENGINEERING ASSIGNMENT NO. 006, REV 1 AND A REVISED TASK EXECUTION PLAN |
| May 28, 2009 | 30 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,398,803 | INCORPORATING AND FUNDING ENGINEERING ASSIGNMENT NO. 024 FOR $2,398,803.00 |
| May 20, 2009 | 29 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE A REVISED ENGINEERING ASSIGNMENT AND TASK EXECUTION PLAN INTO SLIN 0007AT. |
| March 17, 2009 | 28 | CHANGE ORDER | no money | EXTEND SLIN 0007AP |
| January 28, 2009 | 27 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR EA8 SLIN 7BA FROM 9 JAN 09 TO 6 JUL 09. |
| December 12, 2008 | 26 | CHANGE ORDER | +$21,700 | EA 8 REVISION WITH FUNDING FOR $21,700.00 |
| August 28, 2008 | 25 | CHANGE ORDER | +$170,093 | UPDATED COPY |
| July 21, 2008 | 24 | ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | +$99,000 | ACTION 31 - EA 0022 W/ FUNDING |
| July 16, 2008 | 23 | ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | +$261,983 | ACTION 32 - EA 0023 W/ FUNDING |
| July 14, 2008 | 22 | ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | +$127,164 | ACTION 27 - EA 0020 W/ FUNDING |
| July 11, 2008 | 21 | ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | +$144,473 | ACTION 25 - EA 0018 W/ FUNDING |
| July 10, 2008 | 19 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$448,813 | INCORPORATING AND FUNDING ENGINEERING ASSIGNMENT NO. 17 FOR $448,913 |
| July 2, 2008 | 20 | FUNDING ONLY ACTION | +$1,287,000 | ARINC TASK ORDER 0223/MOD 20/ACTION 30 - EA-13 /FUNDING J.A. DONLON |
| June 30, 2008 | 16 | CHANGE ORDER | +$206,767 | EA-21 |
| June 24, 2008 | 18 | CHANGE ORDER | no money | INCORPORATING REVISED PRICING SHEETS FOR ENGINEERING ASSIGNMENT NO. 1 AND 8 |
| May 23, 2008 | 17 | CHANGE ORDER | no money | EXTEND PERIOD OF PERFORMANCE FOR SLIN 0007AK TO 19 SEP 2008 AT NO COST |
| May 12, 2008 | 15 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$857,868 | INFORPORATING AND FUNDING ENGINEERING ASSIGNMENT NO. 14 FOR $857,868.00 |
| May 8, 2008 | 14 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$34,825 | FUNDING AND INCORPORATING ENGINEERING ASSIGNMENT NO. 010 FOR $34,825.00 |
| May 6, 2008 | 11 | CHANGE ORDER | no money | INCORPORATING A DD 254 AND A REVISION 3 TO THE PERFORMANCE WORK STATEMENT |
| May 5, 2008 | 13 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$346,661 | INCORPORATING AND FUNDING ENGINEERING ASSIGNMENT NO. 015 FOR $346,661.00 AND EXTENDING THE PERIOD OF PERFORMANCE FOR SLIN 0007AM TO 9 JAN 2009. |
| April 22, 2008 | 12 | CHANGE ORDER | no money | CORRECT ACCOUNTING CLASSIFICATION FOR SLIN 0007AH |
| April 16, 2008 | 10 | CHANGE ORDER | +$914,046 | ACTION 14 & 21 - EA 009 AND GTL CHANGE |
| April 14, 2008 | 9 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$149,575 | FUNDING AND INCORPORATING ENGINEERING ASSIGNMENT NO. 8 FOR $149,575.00 |
| February 25, 2008 | 8 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$60,674 | EA 0007 ACTION 8 |
| February 21, 2008 | 7 | CHANGE ORDER | no money | REVISED PWS AND TEP |
| February 13, 2008 | 6 | CHANGE ORDER | no money | THE PURPOSE OF THIS NO-COST MODIFICATION (06) IS TO CORRECT THE ACCOUNTING CLASSIFICATION FOR SLIN 0007AK. |
| January 31, 2008 | 5 | CHANGE ORDER | no money | THE PURPOSE OF THIS NO-COST MODIFICATION (05) IS TO EXTEND THE PERIOD OF PERFORMANCE FOR SLIN 0007AJ. |
| November 27, 2007 | 4 | CHANGE ORDER | +$502,631 | EA # 04 |
| October 12, 2007 | 3 | CHANGE ORDER | no money | INCORPORATING A NEW PLC, DRAFTSPERSON, AT NO ADDITIONAL COST. |
| September 26, 2007 | 2 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$67,639 | INCORPORATING AND FUNDING ENGINEERING ASSIGNMENT NOS. 3 AND 5 |
| September 17, 2007 | 1 | OTHER ADMINISTRATIVE ACTION | +$258,380 | ENGINEERING ASSIGNMENT 002, CR 1581 ACTION 1 |
| July 5, 2007 | base | not on file | +$205,325 | NEEW TASK ORDER FOR C/KC-135 SYSTEM SUSTAINMENT AND SUPPORT |