BOOZ ALLEN HAMILTON INC
Federal contract award, Booz Allen Hamilton, $4,604,533
Key CONT_AWD_693JJ625F00020N_6930_693JJ624A000002_6930. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 25 days before this system saw it. One version on record.
Cite this row
9e3ec34a0ca8ddd441b996b3e8e6f09af927753f33b9eb7e13149187b9e03d77The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $4,604,533 | first version | August 15, 2025 | August 11, 2026 | 2026-09-05T00:52:54Z | historical sweep | 9e3ec34a0ca8 |
Archived copy
https://web.archive.org/web/20260923112745/https://www.usaspending.gov/award/CONT_AWD_693JJ625F00020N_6930_693JJ624A000002_6930 captured by this system, September 23, 2026
What the amount is made of
4 recorded actions, so the amount is the award's current total across all of them. 2 of them obligated money. Measured 2026-10-16, when USAspending reported a total obligation of $4,604,533.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| August 11, 2026 | P00003 | EXERCISE AN OPTION | +$2,281,264 | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION YEAR 1 - STORM RRD-52, EXTEND THE POP TO 8/14/2027, AND OBLIGATE FUNDING TO SUPPORT CONTINUED WORK. |
| July 23, 2026 | P00002 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | MODIFICATION TO INCORPORATE LCATS AND CHANGE FRA CORS & COS |
| January 28, 2026 | P00001 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO: 1. CHANGE THE PRIMARY COR TO TOMIKA MONTERVILLE AND THE ALTERNATE COR TO KELSEY COOPER. 2. UPDATE THE TAR CLAUSE (TAR CLASS DEVIATION (CD) 2025-02) FOR INVOICING PAYMENT. "THE CONTRACTOR |
| August 15, 2025 | base | not on file | +$2,323,269 | U.S. DEPARTMENT OF TRANSPORTATION (DOT), FEDERAL RAILROAD ADMINISTRATION (FRA), OFFICE OF RAILROAD DEVELOPMENT (RRD) FOR SUPPORT, TECHNICAL, OVERSIGHT, REVIEW, AND MONITORING (STORM). THIS BPA ORDER SHALL DIRECTLY SUPPORT THE SOUTHCENTRAL REGION (RR |
Last refreshed November 4, 2026 at 2:31 PM UTC.