BOOZ ALLEN HAMILTON INC

Federal contract award, Booz Allen Hamilton, $1,103,018

Key CONT_AWD_693KA922F00212_6920_693KA922D00009_6920. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 365 days before this system saw it. One version on record.

Cite this row

On this site https://evidence.ourrevolution.media/filings/booz-allen-hamilton/CONT_AWD_693KA922F00212_6920_693KA922D00009_6920
At the source https://www.usaspending.gov/award/CONT_AWD_693KA922F00212_6920_693KA922D00009_6920
Observed 2026-09-05, version 1, retrieved 2026-09-05T00:53:34Z
Content hash 9f21fc63dc4cbbecd1c73e064646334a3712a538b7e18176e0f9efe1b38d9738

The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.

Versions

VersionAmountChangeOccurredPublishedRetrievedHow it arrivedContent hash
1
current
$1,103,018first versionSeptember 20, 2022September 5, 20252026-09-05T00:53:34Zhistorical sweep9f21fc63dc4c

Archived copy

https://web.archive.org/web/20260929081605/https://www.usaspending.gov/award/CONT_AWD_693KA922F00212_6920_693KA922D00009_6920 captured by this system, September 29, 2026

What the amount is made of

8 recorded actions, so the amount is the award's current total across all of them. 7 of them obligated money. Measured 2026-10-15, when USAspending reported a total obligation of $1,255,959.

Action dateModificationTypeObligatedDescription as recorded
September 16, 2026P00007EXERCISE AN OPTION+$152,94226TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
September 5, 2025P00006EXERCISE AN OPTION+$170,21926TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
April 21, 2025P00005FUNDING ONLY ACTION+$220,00026TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
September 11, 2024P00004EXERCISE AN OPTION+$132,88626TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
October 25, 2023P00003FUNDING ONLY ACTION+$379,91326TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
September 11, 2023P00002EXERCISE AN OPTIONno money26TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
June 12, 2023P00001FUNDING ONLY ACTION+$50,00026TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS
September 20, 2022basenot on file+$150,00026TH TASK ORDER - PHASE I ENVIRONMENTAL SITE ASSESSMENTS (ESAS) AND RELATED TASKS FOR BIPARTISAN INFRASTRUCTURE LAW (BIL)-FUNDED AIRPORT TRAFFIC CONTROL TOWER (ATCT) PROJECTS