BOOZ ALLEN HAMILTON INC
Federal contract award, Booz Allen Hamilton, $23,019,405
Key CONT_AWD_FA820719F0016_9700_47QTCK18D0004_4732. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 145 days before this system saw it. One version on record.
Cite this row
1b7d7913ea848bf9103509b731aa80e2b33df83e6a4da7ca59073b2b480543feThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $23,019,405 | first version | August 15, 2019 | April 13, 2026 | 2026-09-05T00:52:06Z | historical sweep | 1b7d7913ea84 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
41 recorded actions, so the amount is the award's current total across all of them. 31 of them obligated money. Measured 2026-10-17, when USAspending reported a total obligation of $23,019,405.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| April 13, 2026 | P00040 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| March 25, 2025 | P00039 | FUNDING ONLY ACTION | −$4,560 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| December 5, 2024 | P00038 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| September 27, 2024 | P00037 | OTHER ADMINISTRATIVE ACTION | +$680,177 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| September 10, 2024 | P00036 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| August 15, 2024 | P00035 | OTHER ADMINISTRATIVE ACTION | +$3,256,000 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| July 17, 2024 | P00034 | OTHER ADMINISTRATIVE ACTION | +$166,291 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| May 13, 2024 | P00032 | OTHER ADMINISTRATIVE ACTION | +$414,994 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| April 29, 2024 | P00033 | FUNDING ONLY ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| March 25, 2024 | P00031 | FUNDING ONLY ACTION | −$31,217 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| February 20, 2024 | P00029 | OTHER ADMINISTRATIVE ACTION | −$29,984 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| February 16, 2024 | P00030 | OTHER ADMINISTRATIVE ACTION | +$745,344 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| December 20, 2023 | P00028 | OTHER ADMINISTRATIVE ACTION | −$43,029 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| August 28, 2023 | P00027 | OTHER ADMINISTRATIVE ACTION | +$1,833,027 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| July 5, 2023 | P00026 | OTHER ADMINISTRATIVE ACTION | −$34,208 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| April 24, 2023 | P00025 | OTHER ADMINISTRATIVE ACTION | +$399,461 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| December 19, 2022 | P00024 | FUNDING ONLY ACTION | −$19,019 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| September 28, 2022 | P00023 | FUNDING ONLY ACTION | +$2,459,065 | EXERCISE OPTION 3 AND INCREMENTALLY FUND CLINS 3001, 3002, 3003, 3004 AND 3200. |
| August 18, 2022 | P00022 | OTHER ADMINISTRATIVE ACTION | +$908,740 | EXERCISE OPTION 3 AND INCREMENTALLY FUND CLINS 3001, 3002, 3003, 3004 AND 3200. |
| May 5, 2022 | P00021 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| March 14, 2022 | P00020 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| February 17, 2022 | P00019 | EXERCISE AN OPTION | +$1,209,235 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| January 19, 2022 | P00018 | FUNDING ONLY ACTION | +$1,782,026 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| November 10, 2021 | P00017 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| October 22, 2021 | P00016 | FUNDING ONLY ACTION | +$710,000 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| October 21, 2021 | P00015 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| September 29, 2021 | P00014 | FUNDING ONLY ACTION | +$363,525 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANGEMENT PROGRAM. |
| August 17, 2021 | P00013 | OTHER ADMINISTRATIVE ACTION | +$1,546,220 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANGEMENT PROGRAM. |
| March 25, 2021 | P00012 | OTHER ADMINISTRATIVE ACTION | +$1,284,058 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| February 18, 2021 | P00011 | OTHER ADMINISTRATIVE ACTION | +$1,235,063 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| January 20, 2021 | P00010 | OTHER ADMINISTRATIVE ACTION | +$165,258 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| January 14, 2021 | P00009 | FUNDING ONLY ACTION | +$277,132 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE CYCLE MANAGEMENT PROGRAM. |
| August 18, 2020 | P00008 | OTHER ADMINISTRATIVE ACTION | +$1,252,230 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| April 29, 2020 | P00007 | FUNDING ONLY ACTION | +$579,391 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM |
| March 6, 2020 | P00006 | FUNDING ONLY ACTION | +$702,801 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM |
| February 4, 2020 | P00005 | OTHER ADMINISTRATIVE ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM |
| January 13, 2020 | P00004 | FUNDING ONLY ACTION | +$352,887 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| November 26, 2019 | P00003 | FUNDING ONLY ACTION | +$208,009 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| October 30, 2019 | P00002 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$410,515 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| September 6, 2019 | P00001 | FUNDING ONLY ACTION | no money | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM. |
| August 15, 2019 | base | not on file | +$239,976 | SUSTAINMENT AND DEVELOPMENT OF THE LIFE-CYCLE MANAGEMENT PROGRAM |
Last refreshed November 4, 2026 at 2:31 PM UTC.