BOOZ ALLEN HAMILTON INC
Federal contract award, Booz Allen Hamilton, $51,988,784
Key CONT_AWD_N0042122F3001_9700_N0017819D7264_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 101 days before this system saw it. One version on record.
Cite this row
bb4957227394fe96273de76a2f81147874e2be350126b3dca76f1ab53fdaec63The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $51,988,784 | first version | November 23, 2021 | May 27, 2026 | 2026-09-05T00:51:43Z | historical sweep | bb4957227394 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
86 recorded actions, so the amount is the award's current total across all of them. 81 of them obligated money. Measured 2026-10-18, when USAspending reported a total obligation of $53,999,785.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| July 1, 2026 | P00085 | OTHER ADMINISTRATIVE ACTION | no money | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION; INTEGRATION AND INSTALLATION; VERIFICATION AND VALIDATION; TECHNICAL AND MANAGEMENT, OPERATIONS AND SUSTAINMENT, AND RDTE SUPPORT. |
| June 17, 2026 | P00084 | FUNDING ONLY ACTION | +$2,011,001 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION; INTEGRATION AND INSTALLATION; VERIFICATION AND VALIDATION; TECHNICAL AND MANAGEMENT, OPERATIONS AND SUSTAINMENT, AND RDTE SUPPORT. |
| May 27, 2026 | P00083 | FUNDING ONLY ACTION | +$661,677 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION; INTEGRATION AND INSTALLATION; VERIFICATION AND VALIDATION; TECHNICAL AND MANAGEMENT, OPERATIONS AND SUSTAINMENT, AND RDTE SUPPORT. |
| May 5, 2026 | P00082 | FUNDING ONLY ACTION | +$45,860 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION; INTEGRATION AND INSTALLATION; VERIFICATION AND VALIDATION; TECHNICAL AND MANAGEMENT, OPERATIONS AND SUSTAINMENT, AND RDTE SUPPORT. |
| April 16, 2026 | P00081 | FUNDING ONLY ACTION | +$2,230,354 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION; INTEGRATION AND INSTALLATION; VERIFICATION AND VALIDATION; TECHNICAL AND MANAGEMENT, OPERATIONS AND SUSTAINMENT, AND RDTE SUPPORT. |
| March 12, 2026 | P00080 | FUNDING ONLY ACTION | +$319,611 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| February 4, 2026 | P00079 | FUNDING ONLY ACTION | +$39,946 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| January 30, 2026 | P00078 | FUNDING ONLY ACTION | +$1,289,438 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| January 9, 2026 | P00077 | FUNDING ONLY ACTION | +$1,386,600 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| December 30, 2025 | P00076 | FUNDING ONLY ACTION | +$503,802 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| December 17, 2025 | P00075 | FUNDING ONLY ACTION | +$177,595 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| December 1, 2025 | P00074 | FUNDING ONLY ACTION | +$249,215 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, REQUIREMENTS IDENTIFICATION & DOCUMENTATION, INTEGRATION, VERIFICATION, & RDT&E SUPPORT. |
| November 7, 2025 | P00073 | FUNDING ONLY ACTION | +$314,897 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS. TASKS INCLUDE: REQUIREMENTS DOCUMENTATION INTEGRATION & INSTALLATION VERIFICATION & VALIDATION TECHNICAL & MANAGEMENT, OPERATIONS & SUSTAINMENT, & RDT&E SUPPORT. |
| November 3, 2025 | P00072 | FUNDING ONLY ACTION | +$198,591 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, INTEGRATION AND INSTALLATION, VERIFICATION AND VALIDATION, SUSTAINMENT, AND RDT&E SUPPORT. |
| September 11, 2025 | P00071 | FUNDING ONLY ACTION | +$255,667 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, REQUIREMENTS IDENTIFICATION & DOCUMENTATION, INTEGRATION, VERIFICATION, & RDT&E SUPPORT. |
| August 19, 2025 | P00070 | FUNDING ONLY ACTION | +$1,220,669 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, REQUIREMENTS IDENTIFICATION & DOCUMENTATION, INTEGRATION, VERIFICATION, & RDT&E SUPPORT. |
| July 28, 2025 | P00069 | FUNDING ONLY ACTION | +$188,645 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, REQUIREMENTS IDENTIFICATION & DOCUMENTATION, INTEGRATION, VERIFICATION, & RDT&E SUPPORT. |
| July 1, 2025 | P00068 | FUNDING ONLY ACTION | +$620,285 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, REQUIREMENTS IDENTIFICATION & DOCUMENTATION, INTEGRATION, VERIFICATION, & RDT&E SUPPORT. |
| June 12, 2025 | P00067 | FUNDING ONLY ACTION | +$143,501 | THE PURPOSE OF THIS TASK ORDER MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING TO CLIN 6000. |
| June 2, 2025 | P00066 | FUNDING ONLY ACTION | −$2,609 | ENGINEERING & TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL SUPPORT, INSTALLATION, VERIFICATION, & SUSTAINMENT & RDT&E SUPPORT. |
| April 30, 2025 | P00065 | FUNDING ONLY ACTION | +$120,000 | ENGINEERING & TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL & MANAGEMENT SUPPORT, REQUIREMENTS DOCUMENTATION, INSTALLATION, VALIDATION, & RDT&E SUPPORT. |
| March 24, 2025 | P00064 | FUNDING ONLY ACTION | +$33,517 | INCREMENTALLY FUND AND DEOBLIGATE |
| March 13, 2025 | P00063 | FUNDING ONLY ACTION | +$261,319 | INCREMENTALLY FUND AND DEOBLIGATE |
| February 27, 2025 | P00062 | FUNDING ONLY ACTION | +$4,899,427 | INCREMENT FUNDING AND DEOBLIGATION |
| February 13, 2025 | P00061 | FUNDING ONLY ACTION | +$260,580 | THIS PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING. |
| January 15, 2025 | P00060 | FUNDING ONLY ACTION | +$435,878 | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CLINS 6001, 6002 AND 7001. |
| January 7, 2025 | P00059 | FUNDING ONLY ACTION | +$65,455 | ADMINISTRATIVE CHANGE AND INCREMENTALLY FUND |
| December 9, 2024 | P00058 | FUNDING ONLY ACTION | +$95,500 | INCREMENTALLY FUND AND ADMINISTRATIVE CHANGE |
| November 7, 2024 | P00057 | FUNDING ONLY ACTION | +$2,440,233 | EXERCISE AN OPTION, INCREMENTALLY FUND, AND ADMINISTRATIVE CHANGE |
| October 10, 2024 | P00056 | FUNDING ONLY ACTION | +$341,401 | INCREMENTALLY FUND, DEOBLIGATE AND REALIGN CEILING |
| September 13, 2024 | P00055 | FUNDING ONLY ACTION | −$52,064 | DEOBLIGATE FUNDING AND REALIGN CEILING |
| August 20, 2024 | P00054 | FUNDING ONLY ACTION | +$26,962 | INCREMENTAL FUNDING |
| August 6, 2024 | P00053 | FUNDING ONLY ACTION | +$126,000 | INCREMENTAL FUNDING |
| July 25, 2024 | P00052 | FUNDING ONLY ACTION | +$670,000 | INCREMENTAL FUNDING |
| July 10, 2024 | P00051 | FUNDING ONLY ACTION | +$420,554 | INCREMENTALLY FUND |
| June 4, 2024 | P00050 | FUNDING ONLY ACTION | +$838,455 | INCREMENTALLY FUND AND ADMINISTRATIVE CHANGE |
| May 14, 2024 | P00049 | FUNDING ONLY ACTION | +$588,169 | INCREMENTALLY FUND AND DEOBLIGATE |
| April 24, 2024 | P00048 | FUNDING ONLY ACTION | +$370,408 | DEOBLIGATE, INCREMENTALLY FUND, REALIGN CEILING, AND ADMINISTRATIVE CHANGE |
| April 1, 2024 | P00047 | FUNDING ONLY ACTION | +$1,463,353 | INCREMENTAL FUNDING AND DEOBLIGATE |
| March 11, 2024 | P00046 | FUNDING ONLY ACTION | +$11,162 | INCREMENTAL FUNDING AND DEOBLIGATE |
| March 5, 2024 | P00045 | FUNDING ONLY ACTION | −$208,546 | DEOBLIGATE AND REALIGN CEILING |
| February 14, 2024 | P00044 | FUNDING ONLY ACTION | +$955,041 | INCREMENTALLY FUND |
| January 31, 2024 | P00043 | FUNDING ONLY ACTION | +$203,714 | INCREMENTALLY FUND |
| January 4, 2024 | P00042 | FUNDING ONLY ACTION | +$684,063 | INCREMENTAL FUNDING |
| December 18, 2023 | P00041 | FUNDING ONLY ACTION | +$54,047 | INCREMENTAL FUNDING AND ADMINISTRATIVE CHANGE |
| December 11, 2023 | P00040 | FUNDING ONLY ACTION | +$2,294,087 | INCREMENTAL FUNDING, DEOBLIGATE, AND REALIGN CEILING |
| November 27, 2023 | P00039 | FUNDING ONLY ACTION | +$515,000 | EXERCISE OPTION YEAR II AND INCREMENTALLY FUND |
| November 2, 2023 | P00038 | FUNDING ONLY ACTION | +$8,900 | INCREMENTAL FUNDING |
| October 11, 2023 | P00037 | FUNDING ONLY ACTION | no money | REALIGN CEILING |
| September 7, 2023 | P00036 | FUNDING ONLY ACTION | +$199,031 | INCREMENTAL FUNDING |
| August 16, 2023 | P00035 | FUNDING ONLY ACTION | +$225,064 | DEOBLIGATE, INCREMENTAL FUNDING, AND ADMINISTRATIVE CHANGE |
| August 9, 2023 | P00034 | FUNDING ONLY ACTION | +$532,160 | DEOBLIGATIONS, INCREMENTAL FUNDING AND ADMINISTRATIVE CHANGES |
| July 13, 2023 | P00033 | FUNDING ONLY ACTION | −$94,395 | DEOBLIGATIONS, INCREMENTAL FUNDING, AND ADMINISTRATIVE CHANGE |
| June 29, 2023 | P00032 | FUNDING ONLY ACTION | −$251,571 | DEOBLIGATIONS AND INCREMENTAL FUNDING |
| June 8, 2023 | P00031 | FUNDING ONLY ACTION | +$783,734 | INCREMENTAL FUNDING AND CEILING REALIGN |
| May 8, 2023 | P00030 | FUNDING ONLY ACTION | +$1,629,820 | INCREMENTAL FUNDING |
| May 3, 2023 | P00029 | FUNDING ONLY ACTION | +$141,913 | INCREMENTAL FUNDING |
| April 24, 2023 | P00028 | FUNDING ONLY ACTION | +$800,854 | DEOBLIGATION, INCREMENTAL FUNDING, CEILING REALIGN, ADMINISTRATIVE CHANGES. |
| April 11, 2023 | P00027 | FUNDING ONLY ACTION | +$95,000 | INCREMENTAL FUNDING |
| March 30, 2023 | P00026 | FUNDING ONLY ACTION | +$62,000 | INCREMENTAL FUNDING |
| March 29, 2023 | P00025 | FUNDING ONLY ACTION | +$68,294 | COST/FEE CEILING REALIGN, INCREMENTAL FUNDING, DEOB |
| March 6, 2023 | P00024 | FUNDING ONLY ACTION | +$1,490,388 | DEOBLIGATION AND INCREMENTAL FUNDING |
| February 16, 2023 | P00023 | FUNDING ONLY ACTION | +$781,842 | INCREMENTAL FUNDING AND ADMINISTRATIVE CHANGES |
| February 1, 2023 | P00022 | FUNDING ONLY ACTION | +$135,652 | INCREMENTAL FUNDING AND ADMINISTRATIVE CHANGES |
| January 18, 2023 | P00021 | FUNDING ONLY ACTION | +$748,199 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS AT DIFFERENT STAGES OF THE ENGINEERING LIFECYCLE. TASKS INCLUDE TECHNICAL AND MANAGEMENT SUPPORT, REQUIREMENTS IDENTIFICATION AND DOCUMENTATION, INTEGRATION AND INSTALLATION |
| December 22, 2022 | P00020 | FUNDING ONLY ACTION | +$2,398,175 | INCREMENTAL FUNDING |
| December 7, 2022 | P00019 | FUNDING ONLY ACTION | +$1,044,417 | CEILING REALIGNMENT AND INCREMENTAL FUNDING |
| November 17, 2022 | P00018 | FUNDING ONLY ACTION | +$839,380 | ENGINEER & TECH EXPERTISE TO SUPPORT MSNE PROJECTS AT DIFF STAGES OF ENGINEER LIFECYCLE. TASKS: TECH & MANAGE SUPPORT, REQUIREMENTS ID & DOCUMENT, INTEGRATION & INSTALLATION, VERIFICATION & VALIDATION, OPS & SUSTAINMENT SUPPORT, AND RDT&E SUPPORT. |
| November 14, 2022 | P00017 | FUNDING ONLY ACTION | +$90,000 | ENGINEERING/TECHNICAL SUPPORT MSNE PROJECTS . TASKS INCLUDE TECHNICAL/MANAGEMENT SUPPORT, REQUIREMENTS IDENTIFICATION/DOCUMENTATION, INTEGRATION/INSTALLATION, VERIFICATION, VALIDATION, OPERATIONS, SUSTAINMENT SUPPORT, RDT&E SUPPORT. |
| October 17, 2022 | P00016 | FUNDING ONLY ACTION | +$100,588 | ADMINISTRATIVE CHANGES, DEOBLIGATION AND INCREMENTAL FUNDING |
| September 29, 2022 | P00015 | FUNDING ONLY ACTION | +$62,846 | ENGINEERING AND TECHNICAL EXPERTISE REQUIRED TO SUPPORT MSNE PROJECTS |
| September 14, 2022 | P00014 | FUNDING ONLY ACTION | +$168,561 | ADMINISTRATIVE CHANGES AND INCREMENTAL FUNDING |
| September 1, 2022 | P00013 | FUNDING ONLY ACTION | +$501,916 | INCREMENTAL FUNDING |
| August 10, 2022 | P00012 | FUNDING ONLY ACTION | +$2,078,145 | INCREMENTAL FUNDING AND ADMINISTRATIVE CHANGES. |
| July 11, 2022 | P00011 | FUNDING ONLY ACTION | +$877,024 | ADMINISTRATIVE CHANGES AND INCREMENTAL FUNDING |
| June 29, 2022 | P00010 | FUNDING ONLY ACTION | +$277,207 | ADMINISTRATIVE CHANGES TO SECTION J, ATTACHMENT 1 AND INCREMENTAL FUNDING. |
| June 15, 2022 | P00009 | FUNDING ONLY ACTION | +$145,991 | INCREMENTAL FUNDING |
| June 14, 2022 | P00008 | FUNDING ONLY ACTION | no money | ADMINISTRATIVE CHANGES TO SECTIONS B AND C. |
| May 25, 2022 | P00007 | FUNDING ONLY ACTION | +$1,746,057 | DEOBLIGATION AND INCREMENTAL FUNDING |
| May 4, 2022 | P00006 | FUNDING ONLY ACTION | no money | CEILING REALIGNMENT AND ADMINISTRATIVE CHANGES. |
| April 5, 2022 | P00005 | FUNDING ONLY ACTION | +$323,551 | INCREMENTAL FUNDING |
| March 23, 2022 | P00004 | FUNDING ONLY ACTION | +$733,109 | ADMINISTRATIVE CHANGES AND INCREMENTAL FUNDING |
| March 16, 2022 | P00003 | FUNDING ONLY ACTION | +$88,427 | INCREMENTAL FUNDING |
| March 1, 2022 | P00002 | FUNDING ONLY ACTION | no money | CEILING REALIGNMENT |
| January 28, 2022 | P00001 | OTHER ADMINISTRATIVE ACTION | +$5,349,044 | ADMIN-15 |
| November 23, 2021 | base | not on file | +$50,000 | MSNE AWWARD |
Last refreshed November 4, 2026 at 2:31 PM UTC.