BOOZ ALLEN HAMILTON INC
Federal contract award, Booz Allen Hamilton, $122,933,344
Key CONT_AWD_N6600121F3501_9700_N0017819D7264_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 176 days before this system saw it. One version on record.
Cite this row
e18198a3fec7cf23db612bef5453a99ffcc81b579f16ff0fb589d18b32b7dcb8The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $122,933,344 | first version | February 23, 2021 | March 13, 2026 | 2026-09-05T00:51:32Z | historical sweep | e18198a3fec7 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
34 recorded actions, so the amount is the award's current total across all of them. 29 of them obligated money. Measured 2026-10-18, when USAspending reported a total obligation of $122,933,344.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| March 13, 2026 | P00033 | OTHER ADMINISTRATIVE ACTION | no money | THIS MOD UPDATES ACRNS FOR SUBCLINS 200102 AND 300102 TO HW AND ACRNS FOR SUBCLINS 200103 AND 300103 TO HX, REMOVES EXTRA 0 FROM SUBCLIN 200102 LOA COST CODE, AND ADDS A MISSING 1 TO THE APPROPRIATION NUMBER OF SUBCLIN 200103 LOA. |
| January 30, 2026 | P00032 | FUNDING ONLY ACTION | +$998,217 | THIS MODIFICATION INCREMENTALLY FUNDS OY4 CLINS 8041, 9041, AND 6002 WITH $998,217.00. CLINS 8041 AND 9041 ARE TO BE INCREMENTALLY FUNDED WITH $787,290.00 OF FY24 OPN FUNDS, AND CLIN 6002 IS TO BE FUNDED WITH $210,927.00 OF FY26 OM&N FUNDS. |
| September 23, 2025 | P00031 | FUNDING ONLY ACTION | +$18,023,277 | THIS MOD CREATES CLINS 6005, 6006, 7006, 4041, 4042, 8041, AND 9041, TRANSFERS $1,490,000.00 OF CEILING FROM OY3 TO OY4, AND $9,916,281.14 OF CEILING FROM CLIN 6001 TO 6003, 6005, 6006, 4041, 4042, 8041, UPDATES LABOR HRS, AND FUNDS $18,023,276.53. |
| August 5, 2025 | P00030 | FUNDING ONLY ACTION | −$9,327,064 | THIS MOD (1) DE-OBLIGATES $635,164.17 FROM OPTION YEAR 2 CLINS 2021 AND 3021, (2) DE-OBLIGATES $6,888,900.00 FROM OPTION YEAR 3 CLINS 2031 AND 3031, AND (3) DE-OBLIGATES $1,797,000.00 FROM OPTION YEAR 3 CLINS 8031 AND 9031, TOTALING $9,321,064.17. |
| June 25, 2025 | P00029 | FUNDING ONLY ACTION | +$1,826,211 | (1) CREATE CLINS 6004 AND CLIN 7004, MOVE $373,815.00 OF CEILING FROM 6001 TO 6004 AND $6,000.00 OF CEILING FROM CLIN 7001 TO 7004 (2) UPDATE LABOR HRS., AND (3) ADD FUNDS TO CLINS 6001, 7001, 6002, 7002, 6004, AND 7004 WITH $1,826,211.00. |
| April 7, 2025 | P00028 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PWS REV. 2 (DATED 19 MAR 2025) AND DD254 REV. 2 (DATED 27 MAR 2025). |
| February 27, 2025 | P00027 | EXERCISE AN OPTION | +$9,270,052 | CREATE NEW CLIN, DECREASE CEILING, UPDATE HOURS AND ADD INCREMENTAL FUNDING. |
| February 18, 2025 | P00026 | EXERCISE AN OPTION | +$8,808,396 | THIS PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 4 CLINS 6001, 6002, 7001 AND 7002, AND INCREMENTALLY FUND OPTION YEAR 4 WITH $8,808,396.00 OF FY24 OPN AND OMN, NAVY FUNDS. |
| January 17, 2025 | P00025 | FUNDING ONLY ACTION | +$260,454 | INCREMENTALLY FUND CLINS 2031 AND 3031 WITH $260,454.42 OF FY24 AND FY25 OPN FUNDS |
| December 3, 2024 | P00024 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO ADD G2IT, LLC AS A SUBCONTRACTOR TO CONTRACT NO. N0017819D7264/N6600121F3501. SECTION I-3 (FAR CLAUSE 52.244-2) IS UPDATED AS A RESULT OF THE ADDED SUB-CONTRACTOR. |
| November 25, 2024 | P00023 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO ADD BLOOM CONSULTING, LLC AS A SUBCONTRACTOR TO CONTRACT NO. N0017819D7264/N6600121F3501. SECTION I-3 FOR FAR CLAUSE 52.244-2 IS UPDATED AS A RESULT OF THE ADDED SUB-CONTRACTOR. |
| August 15, 2024 | P00022 | FUNDING ONLY ACTION | +$13,089,782 | MOD INC FUNDS CLINS 2032 AND 3032 WITH $442,789.00, 2031 AND 3031 WITH $1,764,036.17, 4031 AND 5031 WITH $2,422,927.00, 8031 AND 9031 WITH $8,460,029.83, AND MOVES CEILING AND HRS AMONG CLINS 2021, 3021, 2031, 3031, 4031, 5031, 8031, AND 9031 |
| July 1, 2024 | P00021 | FUNDING ONLY ACTION | −$3,765,169 | THIS PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND OPTION YEAR 3 CLINS 2031, 3031, AND 2032 WITH $8,572,758.00 OF FY24 OPN NAVY FUNDS, AND DE-OBLIGATE $12,337,927.00 FROM OPTION YEAR 2 CLINS 8021, 9021, 2021, AND 3021. |
| March 28, 2024 | P00020 | FUNDING ONLY ACTION | +$10,783,990 | THIS PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND OY3 CLINS 2031, 3031, AND 2032 WITH $10,783,990.31 OF FY23/24 OPN AND FY24 OMN, NAVY FUNDS. |
| February 22, 2024 | P00019 | FUNDING ONLY ACTION | +$4,803,856 | THIS PURPOSE OF THIS MODIFICATION IS TO DO THE FOLLOWING: 1. EXERCISE OPTION PERIOD 3 CLINS 2031, 2032, 3031 AND 3032 AND 2. INCREMENTALLY FUND OPTION YEAR 3 WITH $4,803,855.88 OF FY24 OPN AND OMN, NAVY FUNDS. |
| December 7, 2023 | P00018 | FUNDING ONLY ACTION | +$927,616 | THIS MOD (1) INCREMENTALLY FUNDS $927,615.72, (2) TRANSFERS $646,545.81 IN CEILING FROM CLIN 2021 TO 8021 AND $249,069.91 IN CEILING FROM CLIN 3021 TO 9021, AND (3) UPDATES TOTAL STAFF-HOURS OF DIRECT LABOR BECAUSE OF THE ADJUSTED CEILING AMOUNTS. |
| September 29, 2023 | P00017 | FUNDING ONLY ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALLOCATE $343,196.97 OF LABOR FUNDS FROM SUBCLIN 8021/05 TO SUBCLIN 8021/17. |
| September 14, 2023 | P00016 | FUNDING ONLY ACTION | +$9,105,159 | THIS MOD (1) DE-OBS $66K FROM BASE YR. (2) DE-OBS $1.6M FROM OY1 (3) FUND OY2 VIA CLINS 8021 & 9021 (4) FUND OY2 CLINS VIA 2021 & 3021 FOR $2.9M (5) FUNDS OY2 CLINS 2022 & 3022 (6) TRANSFER CEILING AMONG OY2 CLINS & (7) UPDATE LABOR HRS |
| August 16, 2023 | P00015 | FUNDING ONLY ACTION | +$4,866,484 | THIS MOD ADDS KUPONO TECH TO THE LIST OF SUBKTRS UNDER FAR 52.244-2 CHANGES POP END-DATE FOR CLINS 4021 & 5021 TO 30 SEP 2023 CHANGES CEILINGS FOR CLINS 2021, 3021, 4021, & 5021 UPDATES CLINS 2021 AND 4021 HRS & INC. FUNDS $4,866,484.40 FOR OY2. |
| May 31, 2023 | P00014 | FUNDING ONLY ACTION | +$6,070,015 | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND $6,070,015.00 FOR OPTION YEAR 2 |
| May 31, 2023 | P00013 | EXERCISE AN OPTION | −$11,964,032 | THIS MODIFICATION (1) INCREMENTALLY FUNDS $1,643,863.10 FOR OY2, (2) TRANSFER CEILING AMOUNTS FROM BASE YEAR AND OY1, TO OPTION YEAR 2, AND (3) DE-OBLIGATE $2,335,770.76 OF FUNDS FROM THE BASE YEAR, AND $9,962,119.89 OF FUNDS FROM OPTION YEAR 1. |
| April 4, 2023 | P00012 | EXERCISE AN OPTION | −$37,035 | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE $37,035.15 OF FUNDS FROM OPTION PERIOD SLINS 201133 (LABOR) AND 301133 (ODC). |
| February 23, 2023 | P00011 | EXERCISE AN OPTION | +$14,983,124 | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND $1,120,482.00 FOR OPTION YEAR 1. SUBCLIN 201136 WAS ADDED TO INCREMENTALLY FUND $994,741.00 IN SUPPORT OF LABOR. SUBCLIN 201205 WAS ADDED TO INCREMENTALLY FUND $125,741.00 IN SUPPORT OF LABOR. |
| September 29, 2022 | P00010 | FUNDING ONLY ACTION | +$1,120,482 | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND $1,120,482.00 FOR OPTION YEAR 1, IN SUPPORT OF LABOR. |
| July 27, 2022 | P00009 | FUNDING ONLY ACTION | +$12,005,047 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT CLAUSE B-4 ALLOTTED COST SLIN 201110 FROM $420.307.39 TO $420,307.39, AND TO INCREMENTALLY FUND $12,005,046.80 FOR OPTION YEAR 1, IN SUPPORT OF LABOR AND ODC. |
| June 29, 2022 | P00008 | FUNDING ONLY ACTION | +$6,414,734 | THE PURPOSE OF THIS MODIFICATION IS TO (1) REALIGN $14,644,793.08 AND THE RESPECTIVE TOTAL STAFF-HOURS OF DIRECT LABOR FROM BASE TO OY1, AND (2) RE-OBLIGATE $6,414,733.52 TOWARDS OPTION PERIOD 1, CLINS 2011 FOR LABOR AND 3011 FOR ODC. |
| June 13, 2022 | P00007 | FUNDING ONLY ACTION | +$120,983 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE DE-OBLIGATION FUNDING AMOUNT IN P00006 FROM $7,444,737.68 TO $7,323,758.46. |
| April 25, 2022 | P00006 | FUNDING ONLY ACTION | −$7,444,738 | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE $8,071,393.10 OF FUNDS FROM BASE PERIOD CLINS 2001 (LABOR) AND 3001 (ODC). ALL OTHER TERMS AND CONDITIONS ON THE CONTRACT REMAIN THE SAME. |
| February 24, 2022 | P00005 | FUNDING ONLY ACTION | +$12,277,263 | THIS MODIFICATION IS TO INCREMENTALLY FUND OPTION PERIOD 1, CLINS 2011, 2012, 3011, AND 3012 IN THE AMOUNT OF $12,277,262.70. AS A RESULT OF THIS MODIFICATION, THE FUNDING OBLIGATION INCREASES BY $12,277,262.70, FROM $19,716,240.16 TO $31,993,502.86. |
| February 23, 2022 | P00004 | FUNDING ONLY ACTION | +$1,120,405 | THIS MODIFICATION EXERCISES AND INCREMENTALLY FUNDS OPTION PERIOD 1, CLINS 2011, 2012, 3011, AND 3012 FOR $1,120,405.16. SLIN 201101 INCREMENTALLY FUNDS $1,072,708.34 FOR LABOR CLIN 2011. SLIN 301101 INCREMENTALLY FUNDS ODC CLIN 3011 FOR $47,696.82. |
| September 29, 2021 | P00003 | FUNDING ONLY ACTION | +$168,927 | THIS MOD INCREMENTALLY FUNDS $168,927.20. SLIN 200201 INCREMENTALLY FUNDS $162,437.20 SUPPORTING LABOR & SLIN 300201 INCREMENTALLY FUNDS $6,490.00 SUPPORTING ODC. THE TOTAL FUNDED AMOUNT INCREASES BY $168,927.20 FROM $18,426,907.80 TO $18,595,835.00. |
| August 23, 2021 | P00002 | FUNDING ONLY ACTION | +$5,360,346 | THIS MODIFICATION INCORPORATES (1) DD FORM 254 REV-1 DATED 23 JUNE 2021, (2) U.S/ROK SOFA CLAUSE & CONTINUATION OF PERFORMANCE IN WARTIME CLAUSE IAW USFK REG 700-19, (3) DFARS 252.225-7976 (DEV 2018-O0019), & (4) INCREMENTALLY FUNDS $5,360,346.52. |
| June 17, 2021 | P00001 | FUNDING ONLY ACTION | +$12,286,945 | THIS PROVIDES INCREMENTAL FUNDING IN THE AMOUNT OF $12,286,944.68. SLINS 200104-11 WAS ADDED IN SUPPORT OF LABOR. SLINS 300104-07 09-11 WAS ADDED IN SUPPORT OF OCD. TOTAL FUNDED AMOUNT INCREASED BY $12,286,944.68 FROM $779,617.00 TO $13,066,561.68. |
| February 23, 2021 | base | not on file | +$779,617 | THE ENTERPRISE COMMUNICATIONS AND NETWORKS DIVISION (55300) AT NAVAL INFORMATION WARFARE CENTER, PACIFIC (NIWC PACIFIC) HAS IDENTIFIED A REQUIREMENT FOR ENGINEERING, TECHNICAL AND PROGRAMMATIC SERVICES FOR PROGRAM MANAGEMENT WARFARE (PMW) 205. |
Last refreshed November 4, 2026 at 2:31 PM UTC.