BOOZ ALLEN HAMILTON INC
Federal contract award, Booz Allen Hamilton, $30,564,161
Key CONT_AWD_W56KGU19F0018_9700_W15P7T17D0142_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 9 days before this system saw it. 2 versions on record; the current one is first below.
Cite this row
9e5112506c46873b852f0c3ae684242e691665606776e169c0d2f17b78df9a69The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 2 current | $30,564,161 | amount unchanged | September 30, 2019 | April 26, 2025 | 2026-09-05T00:52:01Z | historical sweep | 9e5112506c46 |
| 1 | $30,564,161 | first version | September 30, 2019 | August 27, 2026 | 2026-09-05T00:52:01Z | historical sweep | 900144123b15 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
67 recorded actions, so the amount is the award's current total across all of them. 57 of them obligated money. Measured 2026-10-18, when USAspending reported a total obligation of $30,564,161.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| April 16, 2025 | P00066 | FUNDING ONLY ACTION | −$9,976 | THIS TASK ORDER IS FOR CONTRACTOR PROVIDED SERVICES TO INCLUDE SCIENTIFIC AND ENGINEERING SUPPORT, OPERATIONAL AND ADMINISTRATIVE SUPPORT, AND GENERAL PROGRAM SUPPORT. |
| December 17, 2024 | P00065 | OTHER ADMINISTRATIVE ACTION | −$638,560 | CYBER OFFENSIVE OPERATIONS (CO2)DIVISION ACQUISITION, LABORATORY, AND ENGINERING SUPPORT" |
| August 13, 2024 | P00064 | CHANGE ORDER | +$75,000 | THIS MODIFICATION IS TO ADD $75,000 OF MATERIALS. |
| July 1, 2024 | P00063 | FUNDING ONLY ACTION | +$713,000 | TO FUND MATERIALS IN THE AMOUNT OF $713,000.00. |
| May 29, 2024 | P00062 | FUNDING ONLY ACTION | −$3,217 | THE MODIFICATION IS TO DE-OBLIGATE $3,216.86, FOR DORMANT ACCOUNTS. |
| March 12, 2024 | P00061 | FUNDING ONLY ACTION | +$348,332 | THIS MODIFICATION IS TO FUND MATERIALS. |
| February 26, 2024 | P00060 | FUNDING ONLY ACTION | no money | TO REALIGN TRAVEL FUNDS TO LABOR. |
| February 8, 2024 | P00059 | FUNDING ONLY ACTION | +$1,065,000 | THIS MODIFICATION IS TO ADD FUNDING FOR LABOR AND MATERIAL IN THE AMOUNT OF $1,065,000 |
| December 4, 2023 | P00058 | FUNDING ONLY ACTION | +$1,102,500 | INCREASE INCREMENTAL FUNDING IN THE AMOUNT OF $1,102,500.00 TO THE SUBJECT TASK ORDER. |
| September 11, 2023 | P00057 | OTHER ADMINISTRATIVE ACTION | no money | THIS MODIFICATION IS FOR ADMINISTRATIVE PURPOSES ONLY. TO CORRECT SECTION A OF MODIFICATION P00056. |
| September 5, 2023 | P00056 | FUNDING ONLY ACTION | no money | THIS MODIFICATION IS TO EXERCISE OPTION YEAR FOUR. |
| July 24, 2023 | P00055 | FUNDING ONLY ACTION | −$210,000 | THIS MODIFICATION IS TO DE-OBLIGATE $210,000. |
| June 27, 2023 | P00054 | FUNDING ONLY ACTION | +$1,350,518 | THE PURPOSE OF THIS MODIFICATION IS TO AT $1,350,518.00 TO MATERIALS. |
| June 21, 2023 | P00053 | FUNDING ONLY ACTION | +$3,548 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $3,547.59. |
| June 20, 2023 | P00052 | FUNDING ONLY ACTION | no money | TO UPDATE THE PWS IN SECTION 1.4.2. |
| April 30, 2023 | P00051 | FUNDING ONLY ACTION | +$1,289,690 | THE MODIFICATION IS FOR FUNDING OF $1,289,321.74. |
| April 13, 2023 | P00050 | FUNDING ONLY ACTION | −$679,690 | THIS MODIFICATION IS FOR THE DE-OBLIGATION OF $679,689.59. |
| March 16, 2023 | P00049 | FUNDING ONLY ACTION | +$1,012,736 | THE PURPOSE OF THIS MODIFICATION IS TO FUND MATERIALS IN THE AMOUNT OF $1,012,736.24. |
| February 22, 2023 | P00048 | FUNDING ONLY ACTION | +$340,599 | THE PURPOSE OF THIS MODIFICATION IS TO FUND MATERIALS IN THE AMOUNT OF $340,599.41 |
| January 18, 2023 | P00047 | FUNDING ONLY ACTION | +$1,382,880 | THIS MODIFICATION IS FOR FUNDING IN THE AMOUNT OF $1,382,880.00. |
| January 3, 2023 | P00046 | FUNDING ONLY ACTION | +$1,370,900 | TO PROVIDE FUNDING IN THE AMOUNT OF $1,370,900. |
| September 8, 2022 | P00045 | FUNDING ONLY ACTION | +$500,000 | FUNDING MODIFICATION IN THE AMOUNT OF $500,000. |
| August 30, 2022 | P00044 | EXERCISE AN OPTION | +$868,900 | MODIFICATION TO EXERCISE OPTION YEAR THREE IN THE AMOUNT OF $868,900. |
| July 28, 2022 | P00043 | FUNDING ONLY ACTION | +$466,000 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $466,000.00. |
| June 27, 2022 | P00042 | FUNDING ONLY ACTION | +$9,462 | FUNDING MODIFICATION LABOR $9,461.68. |
| June 9, 2022 | P00041 | FUNDING ONLY ACTION | +$13,980 | FUNDING MODIFICATION LABOR $13,979.60. |
| May 12, 2022 | P00040 | FUNDING ONLY ACTION | +$511,300 | FUNDING MODIFICATION LABOR $376,300 AND MATERIAL $135,000. |
| April 6, 2022 | P00039 | FUNDING ONLY ACTION | +$119,268 | FUNDING MODIFICATION IN THE AMOUNT OF $119,267.88. ARMY FY21 RDTE FUNDING |
| February 25, 2022 | P00038 | FUNDING ONLY ACTION | +$1,568,830 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $1,568,830.02. |
| February 14, 2022 | P00037 | FUNDING ONLY ACTION | +$307,060 | FUNDING MODIFICATION |
| January 5, 2022 | P00035 | FUNDING ONLY ACTION | −$313,967 | DE-OBLIGATION OF $-313,966.63 |
| September 23, 2021 | P00034 | FUNDING ONLY ACTION | +$1,525,073 | OPTION ONE (1) FUNDING |
| September 14, 2021 | P00033 | OTHER ADMINISTRATIVE ACTION | no money | ADMINISTRATIVE |
| August 25, 2021 | P00032 | FUNDING ONLY ACTION | −$574,000 | DE-OBLIGATION |
| August 9, 2021 | P00031 | FUNDING ONLY ACTION | no money | EULA |
| August 2, 2021 | P00030 | FUNDING ONLY ACTION | +$30,000 | FUNDING |
| June 3, 2021 | P00029 | FUNDING ONLY ACTION | +$1,792,559 | FUNDING |
| May 25, 2021 | P00028 | FUNDING ONLY ACTION | +$648,000 | FUNDING |
| May 20, 2021 | P00027 | FUNDING ONLY ACTION | +$85,000 | FUNDING |
| May 10, 2021 | P00026 | FUNDING ONLY ACTION | −$3,000 | DE-OBLIGATION |
| May 4, 2021 | P00025 | FUNDING ONLY ACTION | no money | EULA |
| April 26, 2021 | P00024 | FUNDING ONLY ACTION | +$769,534 | FUNDING |
| April 8, 2021 | P00023 | FUNDING ONLY ACTION | −$547,000 | DE-OBLIGATION |
| March 16, 2021 | P00022 | FUNDING ONLY ACTION | +$620,776 | FUNDING |
| February 25, 2021 | P00021 | FUNDING ONLY ACTION | +$1,375,394 | FUNDING |
| February 25, 2021 | P00020 | FUNDING ONLY ACTION | −$117,000 | DE-OBLIGATION |
| February 8, 2021 | P00019 | FUNDING ONLY ACTION | +$982,000 | FUNDING |
| January 12, 2021 | P00036 | FUNDING ONLY ACTION | +$1,316,700 | FUNDING MODIFICATION |
| January 12, 2021 | P00018 | FUNDING ONLY ACTION | +$320,983 | FUNDING |
| November 12, 2020 | P00017 | FUNDING ONLY ACTION | +$143,000 | FUNDING PROVIDED FOR SHREDDING AND THE DESTRUCTION OF LAB DEVICES. |
| October 13, 2020 | P00016 | FUNDING ONLY ACTION | no money | ADMINISTRATION CHANGES TO MOVE MATERIALS TO LABOR |
| September 28, 2020 | P00015 | FUNDING ONLY ACTION | +$920,107 | THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING AND INCORPORATE FUNDING IN THE AMOUNT OF $920,107.00. |
| September 14, 2020 | P00014 | FUNDING ONLY ACTION | +$933,000 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $933,000.00. |
| August 17, 2020 | P00013 | FUNDING ONLY ACTION | −$1,095,216 | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDING IN THE AMOUNT OF $1,095,216.00. |
| August 11, 2020 | P00012 | FUNDING ONLY ACTION | +$1,195,216 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $1,195,216.00. |
| August 10, 2020 | P00011 | FUNDING ONLY ACTION | −$37,573 | THE PURPOSE OF THIS MODIFICATION IS DE-OBLIGATE FUNDING IN THE AMOUNT OF -$37,572.82 ON THIS CONTRACT. |
| June 30, 2020 | P00010 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$231,500 | FUNDING MATERIALS AND UPDATE SMALL BUSINESS UTILIZATION, LABOR. |
| June 5, 2020 | P00009 | FUNDING ONLY ACTION | +$4,044,709 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $4,023,709.33. |
| March 30, 2020 | P00008 | FUNDING ONLY ACTION | +$848,776 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $848,776.00. |
| March 19, 2020 | P00007 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE ADMINISTRATION OFFICE: FROM: S3101A TO: W56KGU CONTRACT ADMINISTRATION IS HEREBY RETURNED TO THE PROCURING ACTIVITY. |
| February 26, 2020 | P00006 | FUNDING ONLY ACTION | +$859,000 | FUNDING |
| January 29, 2020 | P00005 | FUNDING ONLY ACTION | +$277,100 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $277,100.00. |
| December 30, 2019 | P00004 | FUNDING ONLY ACTION | +$37,000 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $37,000.00. |
| December 3, 2019 | P00003 | OTHER ADMINISTRATIVE ACTION | no money | ADMINISTRATIVE CORRECTION |
| November 27, 2019 | P00002 | FUNDING ONLY ACTION | +$1,057,848 | FUNDING MODIFICATION |
| October 29, 2019 | P00001 | FUNDING ONLY ACTION | +$60,000 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FUNDING IN THE AMOUNT OF $60,000.00. |
| September 30, 2019 | base | not on file | +$300,582 | TASK ORDER IS TO PROVIDE SUPPORT TO THE US ARMY, C5ISR, I2WD, CO2 DIVISION, ATD BRANCH AND ITS SUCCESSOR ORGANIZATIONS AND TO INCORPORATE FUNDING IN THE AMOUNT OF $300,582.00. |
Last refreshed November 4, 2026 at 2:31 PM UTC.