DELOITTE CONSULTING LLP
Federal contract award, Deloitte, $5,183,329
Key CONT_AWD_140D0424F0014_1406_140D0421A0031_1406. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 53 days before this system saw it. One version on record.
Cite this row
e629dfa4cd57362ec28afe5a4d8ac26d934741a666ec27f37e5b4f4b10bbcf3cThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $5,183,329 | first version | January 16, 2024 | July 14, 2026 | 2026-09-05T00:50:10Z | historical sweep | e629dfa4cd57 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
20 recorded actions, so the amount is the award's current total across all of them. 19 of them obligated money. Measured 2026-10-21, when USAspending reported a total obligation of $5,591,874.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| September 22, 2026 | P00019 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$408,545 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - ACTION STOP WORK ORDERS FOR OPTION PERIOD 2 (OP2) COMPLIANCE SUPPORT AND OPTIONAL OFFICE OF GENERAL COUNSEL SUPPORT, REALIGN FUNDING FROM OP 2 TASK 2A TO OP2 TASK 3, ADD FUNDING TO OP 2 |
| July 13, 2026 | P00018 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$141,221 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - REVISE SOW APPENDIX B, REALIGN CEILING OP2 TASKS 3 AND 4 TO TASK 4A AND ADD FUNDING TO TASK 4A |
| March 26, 2026 | P00017 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | −$203,386 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - BASE PERIOD AND OPTION PERIOD 1 DE-OBLIGATION OF FUNDING AND ERROR CORRECTION |
| March 4, 2026 | P00016 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$88,631 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - OP2 OGC SUPPORT - FUNDING |
| January 15, 2026 | P00015 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$60,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - STRATEGIC PLANNING AND OGC SUPPORT |
| January 9, 2026 | P00014 | EXERCISE AN OPTION | +$572,519 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT - EXERCISE OPTION PERIOD 2 |
| September 26, 2025 | P00013 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$86,249 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| June 9, 2025 | P00012 | FUNDING ONLY ACTION | −$3 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| April 11, 2025 | P00011 | FUNDING ONLY ACTION | +$1,320,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| March 5, 2025 | P00010 | FUNDING ONLY ACTION | +$220,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| February 28, 2025 | P00009 | EXERCISE AN OPTION | +$283,545 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| February 27, 2025 | P00008 | FUNDING ONLY ACTION | +$135,022 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| December 13, 2024 | P00007 | FUNDING ONLY ACTION | no money | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| September 4, 2024 | P00006 | FUNDING ONLY ACTION | +$242,328 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| August 12, 2024 | P00005 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$91,497 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| July 30, 2024 | P00004 | FUNDING ONLY ACTION | +$755,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| July 11, 2024 | P00003 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$390,705 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| June 3, 2024 | P00002 | FUNDING ONLY ACTION | +$250,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| March 15, 2024 | P00001 | FUNDING ONLY ACTION | +$500,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
| January 16, 2024 | base | not on file | +$250,000 | BPA ORDER 5 FOR ASSESSMENT AND PROGRAM IMPLEMENTATION SUPPORT |
Last refreshed November 4, 2026 at 2:31 PM UTC.