DELOITTE CONSULTING LLP
Federal contract award, Deloitte, $86,532,618
Key CONT_AWD_47QFMA21F0043_4732_GS00Q14OADU113_4732. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 46 days before this system saw it. One version on record.
Cite this row
327e1be04e637e8deed0fed6f676f76e983e5be4077e8cc5aa2a848e36d4799eThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $86,532,618 | first version | September 27, 2021 | July 21, 2026 | 2026-09-05T00:49:25Z | historical sweep | 327e1be04e63 |
Archived copy
https://web.archive.org/web/20260915171451/https://www.usaspending.gov/award/CONT_AWD_47QFMA21F0043_4732_GS00Q14OADU113_4732 captured by this system, September 15, 2026
What the amount is made of
29 recorded actions, so the amount is the award's current total across all of them. 25 of them obligated money. Measured 2026-10-23, when USAspending reported a total obligation of $110,727,877.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| September 24, 2026 | P00028 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$24,195,259 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. EXTEND 12 MONTH POP 28 SEP 2026 - 27 SEP 2027, OBLIGATE FUNDS. |
| July 21, 2026 | P00027 | FUNDING ONLY ACTION | +$364,360 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. OBLIGATE INCREMENTAL FUNDING. |
| May 18, 2026 | P00026 | FUNDING ONLY ACTION | −$375 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. CEILING REALIGNMENT, DEOBLIGATION OF FUNDS. |
| April 15, 2026 | P00025 | FUNDING ONLY ACTION | −$62,913 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. DEOBLIGATE FUNDS. |
| September 29, 2025 | P00024 | FUNDING ONLY ACTION | +$179,934 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. MODIFICATION IS A FUNDING ACTION. |
| September 25, 2025 | P00023 | EXERCISE AN OPTION | +$20,461,920 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT.MODIFICATION OBLIGATES INCREMENTAL FUNDS. |
| July 25, 2025 | P00022 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,223,269 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. DHRA SURGE SUPPORT. INCREMENTAL FUNDING. |
| April 24, 2025 | P00021 | FUNDING ONLY ACTION | −$187,220 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT - P00021 DE-OBLIGATES FUNDING IN THE AMOUNT OF -$187,219.93. |
| March 20, 2025 | P00020 | FUNDING ONLY ACTION | +$490,152 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT - P00020 INCORPORATES FUNDING IN THE AMOUNT OF $490,151.58 AND REALIGNS CONTRACT CEILING. |
| December 18, 2024 | P00019 | FUNDING ONLY ACTION | −$35,095 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT- P00019 DE-OBLIGATES -$35,095.48 IN FUNDING. |
| September 24, 2024 | P00018 | FUNDING ONLY ACTION | +$373 | MOD 18 - ADMINISTRATIVE CORRECTION TO OPTION PERIOD 04 CEILING + FUNDING FOR OPTION PERIOD 03. ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| September 24, 2024 | P00017 | FUNDING ONLY ACTION | +$17,718,346 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT - MODIFICATION P00017 EXERCISES OPTION YEAR 3, ACCEPTS A REVISED PROPOSAL, AND INCORPORATES $17,718,346.44 IN FUNDING. |
| June 27, 2024 | P00016 | FUNDING ONLY ACTION | +$400,000 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT - MODIFICATION P00016 INCORPORATES INCREMENTAL FUNDING IN THE AMOUNT OF $400,000.00 |
| April 30, 2024 | P00015 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$861,901 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. MODIFICATION P00015 INCORPORATES AN REVISED RFP ATTACHMENT 2 - SOLICITATION & TASK ORDER CLAUSES AND PROVISIONS AND PWS, ACCEPTS A REVISED PROPOSAL, AND APPLIES INCREMENTAL FUNDING. |
| March 11, 2024 | P00014 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | ENTERPRISE PROGRAM MANAGEMENT SUPPORT. MODIFICATION P00014 REMOVED THE QUALITY ASSURANCE SURVEILLANCE PLAN (QASP), RFP ATTACHMENT 6, FROM THE TASK ORDER. |
| September 28, 2023 | P00013 | EXERCISE AN OPTION | +$198,604 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| September 26, 2023 | P00012 | EXERCISE AN OPTION | +$14,567,627 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| June 20, 2023 | P00011 | OTHER ADMINISTRATIVE ACTION | no money | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| April 27, 2023 | P00010 | FUNDING ONLY ACTION | +$5,920 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| April 14, 2023 | P00009 | OTHER ADMINISTRATIVE ACTION | +$564 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| January 4, 2023 | P00008 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$408,993 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| September 27, 2022 | P00007 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$15,268,664 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| August 19, 2022 | P00006 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$60,986 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| July 13, 2022 | P00005 | OTHER ADMINISTRATIVE ACTION | +$375,653 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| April 13, 2022 | P00004 | FUNDING ONLY ACTION | +$385,572 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| April 1, 2022 | P00003 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$638,963 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| December 3, 2021 | P00002 | OTHER ADMINISTRATIVE ACTION | no money | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| November 2, 2021 | P00001 | OTHER ADMINISTRATIVE ACTION | no money | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
| September 27, 2021 | base | not on file | +$13,206,421 | ENTERPRISE PROGRAM MANAGEMENT SUPPORT |
Last refreshed November 4, 2026 at 2:31 PM UTC.