DELOITTE CONSULTING LLP
Federal contract award, Deloitte, $3,106,959
Key CONT_AWD_70B06C25F00000156_7014_70B06C24A00000049_7014. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 178 days before this system saw it. One version on record.
Cite this row
8d2d074318e1807f6926df05a9641744f9d0251120e5269281c32baa5e9cf468The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $3,106,959 | first version | February 21, 2025 | March 11, 2026 | 2026-09-05T00:50:25Z | historical sweep | 8d2d074318e1 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
12 recorded actions, so the amount is the award's current total across all of them. 9 of them obligated money. Measured 2026-10-21, when USAspending reported a total obligation of $3,106,959.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| March 11, 2026 | P00011 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$99,000 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE POP THROUGH 3/17/2026. |
| March 3, 2026 | P00010 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$99,000 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE POP THROUGH 3/11/26. |
| February 20, 2026 | P00009 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF P00009 IS TO DO A NO COST EXTENSION. |
| January 21, 2026 | P00008 | CHANGE ORDER | no money | MODIFICATION TO REALIGN THE LABOR MIX IN OPTION PERIOD 1 TO ENSURE OPTIMAL SUPPORT FOR ALL TASK ORDER ACTIVITIES. |
| December 31, 2025 | P00007 | CHANGE ORDER | +$1,042,386 | MODIFICATION TO REVISE SCOPE AND STRUCTURE OF OPTION PERIOD 1. |
| December 19, 2025 | P00006 | FUNDING ONLY ACTION | +$98,768 | 99K FUNDING MODIFICATION TO EXTEND THE TASK ORDER. |
| September 12, 2025 | P00005 | CHANGE ORDER | no money | MODIFICATION TO TRANSITION TASK ORDER FROM LABOR HOUR TO FFP FOR OPTION PERIOD 2. |
| September 5, 2025 | P00004 | CHANGE ORDER | +$307,289 | MODIFICATION TO CHANGE STRUCTURE OF OPTION PERIOD 1. |
| August 20, 2025 | P00003 | EXERCISE AN OPTION | +$828,816 | MODIFICATION TO EXERCISE OPTION PERIOD 1. |
| April 24, 2025 | P00002 | FUNDING ONLY ACTION | +$243,501 | MODIFICATION TO FULLY FUND THE BASE PERIOD OF THE POP. |
| April 15, 2025 | P00001 | FUNDING ONLY ACTION | +$200,000 | ADD INCREMENTAL FUNDING TO PROGRAM MANAGEMENT AND DATA ANALYTICS |
| February 21, 2025 | base | not on file | +$188,199 | PROGRAM MANAGEMENT AND DATA ANALYTICS |
Last refreshed November 4, 2026 at 2:31 PM UTC.