DELOITTE CONSULTING LLP
Federal contract award, Deloitte, $42,877,500
Key CONT_AWD_TIRNO11D000160004_2050_TIRNO11D00016_2050. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 516 days before this system saw it. One version on record.
Cite this row
3069201f551f0f123846b158c5ddae8925eb217d4421291493eb82f951e3bfbcThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $42,877,500 | first version | August 28, 2012 | April 7, 2025 | 2026-09-05T00:49:28Z | historical sweep | 3069201f551f |
Archived copy
https://web.archive.org/web/20260915180910/https://www.usaspending.gov/award/CONT_AWD_TIRNO11D000160004_2050_TIRNO11D00016_2050 captured by this system, September 15, 2026
What the amount is made of
40 recorded actions, so the amount is the award's current total across all of them. 14 of them obligated money. Measured 2026-10-23, when USAspending reported a total obligation of $42,877,500.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| April 7, 2025 | 39 | OTHER ADMINISTRATIVE ACTION | no money | ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION AND TESTING GROUP?S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFI |
| September 30, 2020 | 38 | FUNDING ONLY ACTION | −$0 | ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION AND TESTING GROUP?S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFICE |
| July 29, 2018 | 37 | FUNDING ONLY ACTION | −$171,981 | ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION AND TESTING GROUP?S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFICE |
| June 19, 2017 | 36 | FUNDING ONLY ACTION | −$78,155 | IGF::CT::IGF FOR CRITICAL FUNCTIONS - ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION AND TESTING GROUP?S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFICE |
| March 8, 2017 | 35 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| July 19, 2016 | 34 | FUNDING ONLY ACTION | −$171,109 | IGF::CT::IGF FOR CRITICAL FUNCTIONS - ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION AND TESTING GROUP?S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFICE |
| March 30, 2016 | 33 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| March 29, 2016 | 32 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| March 23, 2016 | 31 | CHANGE ORDER | −$1,266,350 | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IN ACCORDANCE WITH FAR 4.804-1(A)(1), THE CONTRACTING OFFICER HAS RECEIVED EVIDENCE OF RECEIPT AND ACCEPTANCE OF THE GOODS AND/OR SERVICES.THEREFORE, EXCESS FUNDS HAVE BEEN DEOBLIGATED AND THIS ORDER IS CONSIDERED CLOSED. |
| March 17, 2016 | 30 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| March 10, 2016 | 29 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF |
| March 10, 2016 | 28 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| February 24, 2016 | 27 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IGF::CT::IGF |
| January 13, 2016 | 26 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING |
| December 22, 2015 | 25 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF FOR CRITICAL FUNCTIONS - CONTRACTOR TECHNICAL SUPPORT |
| December 22, 2015 | 24 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF |
| December 16, 2015 | 23 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF - FUNDING ONLY MODIFICATION (REALIGNING FUNDS) |
| August 5, 2015 | 22 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$135,215 | IGF::CT::IGF FOR CRITICAL FUNCTIONS - MISSION CRITICAL WORK FOR ACA. |
| July 23, 2015 | 21 | CHANGE ORDER | +$2,050,000 | IGF::CT::IGF - IMPLEMENTATION AND TESTING |
| June 11, 2015 | 20 | EXERCISE AN OPTION | +$147,216 | IGF::CT::IGF FOR CRITICAL FUNCTIONS - IMPLEMENTATION AND TESTING FOR THE IRS ACA PROGRAM |
| December 4, 2014 | 19 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF ADMIN MOD TO CORRECT PERIOD OF PERFORMANCE ON OPTION YEAR 2 LINE ITEMS |
| September 24, 2014 | 18 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF ADMINISTRATIVE MODIFICATION TO CORRECT FUNDING TOTALS. |
| September 10, 2014 | 17 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CT::IGF INCORPORATE REVISED PWS WHICH WAS USED FOR RENEGOTIATION OF PRICE AND AGREED TO IN MODIFICATION 16. |
| August 29, 2014 | 16 | EXERCISE AN OPTION | +$13,506,050 | IGF::CT::IGF OPTION YEAR 2 EXERCISE AND FULLY FUND |
| August 14, 2014 | 15 | FUNDING ONLY ACTION | no money | IGF::CL::IGF REALLOCATION OF FUNDS. |
| August 1, 2014 | 14 | FUNDING ONLY ACTION | −$678,972 | IGF::CL::IGF THIS IS A SYSTEM GENERATED DEOBLIGTATION MODIFICATION. |
| July 30, 2014 | 13 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CL::IGF THIS MODIFICATION IS BEING ISSUED TO MAKE ADMINISTRATIVE CHANGES TO THE PWS WHICH ARE AGREED UPON BY BOTH THE VENDOR AND THE PROGRAM OFFICE. |
| March 11, 2014 | 12 | FUNDING ONLY ACTION | no money | IGF::CL::IGF THIS MODIFICATION IS BEING ISSUED TO REALLOCATE FUNDS FROM SUBTASK 7 TO SUBTASK 9. |
| February 23, 2014 | 11 | CHANGE ORDER | no money | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO REALLOCATE FUNDING ON CLIN 0004_SUBTASK 4 TO CLINS 0004A AND 0004C IN THE BASE PERIOD USING FUNDS FROM LINE ITEMS 0212 AND 0213. |
| February 20, 2014 | 9 | CHANGE ORDER | no money | IGF::CL::IGF. THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING FROM THE ATTACHED LINE ITEMS 0235-0237 AND 0299 TO CLINS 1008-1012 IN OPTION YEAR 1 ON THIS SAID ORDER IN THE AMOUNT OF $1,877,338.07. |
| February 13, 2014 | 10 | CHANGE ORDER | no money | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO REALLOCATE FUNDING ON CLIN 0011_SUBTASK 11 IN THE BASE PERIOD USING FUNDS FROM LINE ITEM 0235. |
| February 10, 2014 | 6 | CHANGE ORDER | no money | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO REALLOCATED FUNDING FOR OPTION YEAR 1 ON THIS SAID ORDER. |
| January 30, 2014 | 8 | CHANGE ORDER | no money | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO REALLOCATE FUNDING ON CLIN 0004_SUBTASK 4 TO CLINS 0004A AND 0004C IN THE BASE PERIOD USING FUNDS FROM LINE ITEMS 0212 AND 0213. |
| January 27, 2014 | 7 | FUNDING ONLY ACTION | no money | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO REALLOCATE FUNDING ON CLIN 0004_SUBTASK 4 IN THE BASE PERIOD USING FUNDING ON LINE ITEMS 0212 AND 0213. |
| September 27, 2013 | 5 | OTHER ADMINISTRATIVE ACTION | no money | IGF::CL::IGF THIS MODIFICATION IS BEING ISSUED TO CORRECT MISCALCULATIONS MADE IN MODIFICATION 4. |
| September 25, 2013 | 4 | FUNDING ONLY ACTION | +$1,791,742 | IGF::CL::IGF THIS MODIFICATION IS BEING ISSUED TO FULLY FUND OPTION YEAR 1 SUBTASKS 7-9. |
| August 22, 2013 | 3 | FUNDING ONLY ACTION | +$10,805,191 | IGF::CL::IGF. THIS MODIFICATION IS BEING ISSUED TO FULLY FUND AND INCREMENTALLY FUND OPTION YEAR 1 UNDER SUBTASKS 2-12 ON THIS SAID ORDER. |
| August 19, 2013 | 2 | CHANGE ORDER | no money | IGF::CL::IGF. THIS MODIFICATION IS TO INCORPORATE A REVISED MONTHLY PAYMENT SCHEDULE ON THIS SAID ORDER FROM CEILING INCREASED PROCESSED AND REVISED PROPOSAL RECEIVED FROM THE DELOITTE CONSULTING. |
| July 23, 2013 | 1 | CHANGE ORDER | +$5,180,264 | IGF::CL::IGF. THIS MODIFICATION IS ISSUED TO PROCESS A CEILING INCREASE IN THE BASE AND OPTION PERIODS UNDER SUBTASKS 4,9 AND 11 ON THIS SAID ORDER. |
| August 28, 2012 | base | not on file | +$11,628,389 | IGF::CT::IGF ACQUIRE CONTRACTOR TECHNICAL SERVICES TO SUPPORT THE IMPLEMENTATION&TESTING GROUP S MISSION TO DELIVER WORLD CLASS IMPLEMENTATION AND TESTING SUPPORT SERVICES TO THE PROJECTS WITHIN THE PATIENT PROTECTION AND AFFORDABLE CARE ACT (PPACA) PMO OFFICE |
Last refreshed November 4, 2026 at 2:31 PM UTC.