GENERAL DYNAMICS INFORMATION TECHNOLOGY, INC.
Federal contract award, General Dynamics Information Technology, $1,348,799
Key CONT_AWD_15PTDD25F00000003_1550_15PTDD20A00000001_1550. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 51 days before this system saw it. One version on record.
Cite this row
1bcd2e8b18b6cbb6236441601af3623f7b22c4a51e2d123c27cd9ee8f341774eThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $1,348,799 | first version | January 29, 2025 | July 16, 2026 | 2026-09-05T01:10:11Z | historical sweep | 1bcd2e8b18b6 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
12 recorded actions, so the amount is the award's current total across all of them. 8 of them obligated money. Measured 2026-09-13, when USAspending reported a total obligation of $1,348,799.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| July 15, 2026 | P00011 | FUNDING ONLY ACTION | +$40,069 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)- INCREMENTAL FUNDING |
| May 7, 2026 | P00010 | CHANGE ORDER | +$234,083 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)- ADD FUNDING AND EXTEND POP |
| April 10, 2026 | P00009 | CHANGE ORDER | −$85,211 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)-TO CHANGE THE PERIOD OF PERFORMANCE (POP) AND DE-OBLIGATE FUNDING. |
| April 1, 2026 | P00008 | OTHER ADMINISTRATIVE ACTION | no money | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)-TO CORRECT THE PERIOD OF PERFORMANCE (POP) FOR BASE YEAR CLIN 0001. |
| March 27, 2026 | P00007 | OTHER ADMINISTRATIVE ACTION | no money | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)-TO CORRECT THE PERIOD OF PERFORMANCE (POP) FOR OPTION YEAR 1. |
| January 26, 2026 | P00006 | OTHER ADMINISTRATIVE ACTION | no money | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)-NO COST EXTENSION |
| September 30, 2025 | P00005 | FUNDING ONLY ACTION | +$588,080 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)- INCREMENTAL FUNDING. |
| September 9, 2025 | P00004 | FUNDING ONLY ACTION | +$98,000 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)- INCREMENTAL FUNDING. |
| June 18, 2025 | P00003 | FUNDING ONLY ACTION | +$69,277 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE)- INCREMENTAL FUNDING. |
| June 5, 2025 | P00002 | OTHER ADMINISTRATIVE ACTION | no money | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE), COR CHANGE. |
| May 7, 2025 | P00001 | FUNDING ONLY ACTION | +$112,000 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE), INCREMENTAL FUNDING. |
| January 29, 2025 | base | not on file | +$292,500 | BPA CALL ORDER, TASK 4, TECHNOLOGY INNOVATION (SOLUTION ARCHITECTURE), |
Last refreshed November 4, 2026 at 2:31 PM UTC.