GENERAL DYNAMICS INFORMATION TECHNOLOGY, INC.
Federal contract award, General Dynamics Information Technology, $92,054,243
Key CONT_AWD_GSQ0015AJ0043_4732_GS00Q09BGD0025_4735. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 479 days before this system saw it. One version on record.
Cite this row
95d55934c733c5384d0eae413d6d397681666c10f939f4a95f45aaa61d1b487dThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $92,054,243 | first version | March 10, 2015 | May 14, 2025 | 2026-09-05T01:08:48Z | historical sweep | 95d55934c733 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
56 recorded actions, so the amount is the award's current total across all of them. 48 of them obligated money. Measured 2026-09-15, when USAspending reported a total obligation of $92,054,243.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| May 13, 2025 | PO053 | FUNDING ONLY ACTION | −$173,058 | PURPOSE OF MODIFICATION 1. DEOBLIGATE FUNDING ALL MIGRATED CLINS. 2. UPDATE INCREMENTAL FUNDING TABLE, ATTACHMENT G. 3. CLOSEOUT CONTRACT. |
| October 17, 2023 | PS52 | FUNDING ONLY ACTION | no money | PURPOSE OF MODIFICATION 1. DEOBLIGATE FUNDING FROM CLINS 0001 THROUGH 4004. 2. UPDATE INCREMENTAL FUNDING TABLE, ATTACHMENT G. |
| October 17, 2023 | PS052 | FUNDING ONLY ACTION | no money | PURPOSE OF MODIFICATION 1. DEOBLIGATE FUNDING FROM CLINS 0001 THROUGH 4004. 2. UPDATE INCREMENTAL FUNDING TABLE, ATTACHMENT G. |
| March 17, 2023 | P00052 | FUNDING ONLY ACTION | −$5,678,651 | PURPOSE OF MODIFICATION 1. DEOBLIGATE FUNDING FROM CLINS 0001 THROUGH 4004. 2. UPDATE INCREMENTAL FUNDING TABLE, ATTACHMENT G. |
| January 6, 2020 | PS51 | FUNDING ONLY ACTION | −$421,249 | DE-OBLIGATE FUNDING |
| September 20, 2019 | PS50 | FUNDING ONLY ACTION | −$205,465 | DE-OBLIGATE FUNDING |
| September 10, 2019 | PS49 | FUNDING ONLY ACTION | −$2,155,227 | DE-OBLIGATE AND RE-OBLIGATE FUNDING |
| August 14, 2019 | PS48 | FUNDING ONLY ACTION | −$224,370 | DE-OBLIGATE AND OBLIGATE FUNDING |
| July 11, 2019 | PS47 | FUNDING ONLY ACTION | +$2,559,687 | DE-OBLIGATE FUNDING AND ADD INCREMENTAL FUNDING |
| May 28, 2019 | PS46 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$3,928,190 | RE-OBLIGATE FUNDING, ADD FUNDING, UPDATE AFDP, GLOBAL NAME CHANGE TO DC3/CTA |
| May 2, 2019 | PS45 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$825,756 | INCREASE CEILING ADD FUNDING |
| March 15, 2019 | PO44 | FUNDING ONLY ACTION | +$6,910,000 | ADD FUNDING |
| March 1, 2019 | PS43 | EXERCISE AN OPTION | +$1,626,006 | EXERCISE OPTION, INCREASE CEILING ADD FUNDING |
| February 22, 2019 | PS42 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,384,407 | REALIGN UNUSED CEILING, INCREASE CEILING ADD FUNDING |
| January 18, 2019 | PS41 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | REALIGNED UNUSED CEILING FROM BP, OP1 TO OP3 |
| January 3, 2019 | PO40 | FUNDING ONLY ACTION | +$3,265,056 | ADD FUNDING |
| December 21, 2018 | PS39 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | REALIGN CEILING FROM OY4 TO OY3 |
| September 20, 2018 | PS38 | FUNDING ONLY ACTION | +$6,782,877 | REALIGN FUNDING |
| September 7, 2018 | PS37 | FUNDING ONLY ACTION | −$17,868 | DE-OBLIGATE FUNDING TO BE MOVED |
| August 1, 2018 | PS36 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$880,352 | REALIGN CEILING ADD FUNDING |
| June 17, 2018 | PO35 | FUNDING ONLY ACTION | +$9,618,571 | FUNDING |
| May 15, 2018 | PO34 | FUNDING ONLY ACTION | +$987,482 | INCREMENTAL FUNDING |
| April 26, 2018 | PS33 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,624,323 | REALIGN CEILING ADD FUNDING |
| April 11, 2018 | PS32 | FUNDING ONLY ACTION | −$300,000 | DEOB FUNDING |
| March 1, 2018 | PO31 | EXERCISE AN OPTION | +$3,830,000 | EXERCISE OPTION YEAR 3 ADD FUNDING |
| January 8, 2018 | PO30 | FUNDING ONLY ACTION | +$1,400,000 | RE-OBLIGATE FUNDING |
| January 2, 2018 | PS29 | FUNDING ONLY ACTION | −$1,400,000 | DE-OBLIGATE FUNDING |
| December 21, 2017 | PS28 | OTHER ADMINISTRATIVE ACTION | no money | UPDATE SECTION C, H |
| September 28, 2017 | PO27 | FUNDING ONLY ACTION | +$118,119 | IGF::OT::IGF ADD FUNDING INCORPORATE KEY PERSONNEL CHANGE |
| September 11, 2017 | PS26 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$9,912,455 | IGF::OT::IGF REALIGN CEILING, ADD FUNDING |
| July 25, 2017 | PS25 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$5,184,309 | IGF::OT::IGF |
| May 26, 2017 | PO24 | FUNDING ONLY ACTION | +$2,450,000 | IGF::OT::IGF INCREMENTAL FUNDING |
| May 11, 2017 | PO23 | FUNDING ONLY ACTION | +$40,000 | IGF::OT::IGF ADD FUNDING AND REVISED DD254 |
| March 28, 2017 | PS22 | FUNDING ONLY ACTION | +$120,000 | IGF::OT::IGF REALIGN FUNDING ADD INCREMENTAL FUNDING |
| March 9, 2017 | PO21 | FUNDING ONLY ACTION | +$1,350,000 | IGF::OT::IGF INC FUNDING |
| February 24, 2017 | PO20 | EXERCISE AN OPTION | +$3,800,000 | IGF::OT::IGF |
| February 16, 2017 | PS19 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,340,000 | IGF::OT::IGF REALIGN CEILING, ADD FUNDING |
| December 22, 2016 | PO18 | FUNDING ONLY ACTION | +$2,389,121 | IGF::OT::IGF INCREMENTAL FUNDING |
| November 30, 2016 | PS17 | FUNDING ONLY ACTION | +$1,050,000 | IGF::OT::IGF |
| October 7, 2016 | PS16 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | IGF::OT::IGF REALIGN CEILING, REALIGN FUNDING |
| September 30, 2016 | PO15 | FUNDING ONLY ACTION | +$31,874 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J OF THE CONFORMED VERSION OF THE TASK ORDER. |
| September 29, 2016 | PO14 | FUNDING ONLY ACTION | +$1,581,544 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J OF THE CONFORMED VERSION OF THE TASK ORDER. |
| July 20, 2016 | PO13 | FUNDING ONLY ACTION | +$1,011,344 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J ATTACHMENTS G OF THE CONFORMED VERSION OF THE TASK ORDER. |
| June 14, 2016 | PO12 | FUNDING ONLY ACTION | +$254,646 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING, MAKE ADMINISTRATIVE CHANGES, AND UPDATE SECTIONS B AND J ATTACHMENTS G AND H OF THE CONFORMED VERSION OF THE TASK ORDER. |
| May 28, 2016 | PS11 | OTHER ADMINISTRATIVE ACTION | +$2,334,931 | IGF::OT::IGF INC FUNDING CHANGES TO SECTION C |
| April 15, 2016 | PS10 | OTHER ADMINISTRATIVE ACTION | −$6,623 | IGF::OT::IGF DEOBLIGATE UNEARNED FEE, ADD MANPOWER REPORTING REQUIREMENT |
| March 8, 2016 | PO09 | EXERCISE AN OPTION | +$7,358,000 | IGF::OT::IGF EXERCISE OPTION YEAR 1 ADD INCREMENTAL FUNDING |
| February 17, 2016 | PO08 | FUNDING ONLY ACTION | +$863,954 | IGF::OT::IGF INCREMENTAL FUNDING |
| November 30, 2015 | PO07 | FUNDING ONLY ACTION | +$2,138,360 | IGF::OT::IGF ADD INCREMENTAL FUNDING |
| November 20, 2015 | PS06 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO REALIGN CEILING AND UPDATE SECTIONS B AND J ATTACHMENT G OF THE CONFORMED VERSION OF THE TASK ORDER. |
| September 17, 2015 | PO05 | FUNDING ONLY ACTION | +$1,066,000 | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J ATTACHMENT G OF THE CONFORMED VERSION OF THE TASK ORDER. SEE THE ATTACHED SF30 CONTINUATION PAGE, CONFORMED VERSION OF THE TASK ORDER, AND SECTION J ATTACHMENT G INCREMENTAL FUNDING TABLE. |
| July 31, 2015 | PO04 | FUNDING ONLY ACTION | +$866,765 | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J ATTACHMENT G OF THE CONFORMED VERSION OF THE TASK ORDER. SEE THE ATTACHED SF30 CONTINUATION PAGE, CONFORMED VERSION OF THE TASK ORDER, AND SECTION J ATTACHMENT G INCREMENTAL FUNDING TABLE. |
| July 7, 2015 | PO03 | FUNDING ONLY ACTION | +$1,604,260 | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND UPDATE SECTIONS B AND J ATTACHMENT G OF THE CONFORMED VERSION OF THE TASK ORDER. SEE THE ATTACHED SF30 CONTINUATION PAGE, CONFORMED VESION OF THE TASK ORDER, AND SECTION J ATTACHMENT G INCREMENTAL FUNDING TABLE. |
| June 5, 2015 | PS02 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE ABILITY TO TRAVEL TO OCONUS LOCATIONS, INCLUDE AN ADDITIONAL KEY PERSONNEL POSITION, UPDATE SECURITY REQUIREMENTS TO INCLUDE SENSITIVE COMPARTMENTED INFORMATION (SCI), AND UPDATE SECTIONS C AND H OF THE CONFORMED VERSION OF THE TASK ORDER. |
| May 18, 2015 | PS01 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,860,505 | ''IGF::OT::IGF'' THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING, UPDATE THE AWARD FEE DETERMINATION PLAN (AFDP), INCORPORATE THE FINAL DEPARTMENT OF DEFENSE (DD) 254 FORM, MAKE ADMINISTRATIVE CHANGES, AND UPDATE SECTIONS B AND J ATTACHMMENTS C, G, AND H OF THE CONFORMED VERSION OF THE TASK ORDER. |
| March 10, 2015 | base | not on file | +$5,287,860 | ''IGF::OT::IGF'' TASK ORDER (TO) GSQ0015AJ0043 IS HEREBY AWARDED TO COMPUTER SCIENCES CORPORATION (CSC) TO PROVIDE THE DEPARTMENT OF DEFENSE (DOD), DEFENSE CYBER CRIME CENTER (DC3), DEFENSE CYBER INVESTIGATION TRAINING ACADEMY (DCITA) SUPPORT IN DCITA OPERATIONS, CURRICULUM DEVELOPMENT, CURRICULUM DELIVERY, COURSEWARE AND TRAINING SUPPORT, AND THE ADMINISTRATION AND MAINTENANCE OF DCITA INFORMATION TECHNOLOGY. THE PERIOD OF PERFORMANCE FOR THIS TO WILL BE MARCH 10, 2015 MARCH 09, 2020. THE TOTAL VALUE OF THE TO WILL BE $83,625,996 AND THE TO WILL BE FUNDED IN THE AMOUNT OF $5,187,860 AT AWARD. |
Last refreshed November 4, 2026 at 2:31 PM UTC.