GENERAL DYNAMICS INFORMATION TECHNOLOGY, INC.
Federal contract award, General Dynamics Information Technology, $11,069,710
Key CONT_AWD_HC104717F0067_9700_GS35F088AA_4732. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 456 days before this system saw it. One version on record.
Cite this row
24f8331c01e954db992818079fb1d14c36682bbbc302e13d2ff6b14c8b7ef7e8The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $11,069,710 | first version | June 30, 2017 | June 6, 2025 | 2026-09-05T01:09:22Z | historical sweep | 24f8331c01e9 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
37 recorded actions, so the amount is the award's current total across all of them. 29 of them obligated money. Measured 2026-09-14, when USAspending reported a total obligation of $11,069,710.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| June 6, 2025 | P00036 | CLOSE OUT | −$14,723 | TASK 4 SECURE MOBILITY/UNIFIED O&M SUPPO |
| July 30, 2024 | P00035 | OTHER ADMINISTRATIVE ACTION | no money | TASK 4 SECURE MOBILITY/UNIFIED O&M SUPPO |
| July 26, 2024 | P00034 | OTHER ADMINISTRATIVE ACTION | −$13,204 | TASK 4 SECURE MOBILITY/UNIFIED O&M SUPPO |
| June 23, 2022 | P00033 | FUNDING ONLY ACTION | +$190,413 | TASK 4 SECURE MOBILITY/UNIFIED O&M SUPPO |
| February 28, 2022 | P00032 | FUNDING ONLY ACTION | +$816,785 | NETWORK SUPPORT WHCA |
| November 18, 2021 | P00031 | OTHER ADMINISTRATIVE ACTION | no money | NETWORK ENGINEERING SUPPORT SERVICES. EO14042 |
| September 21, 2021 | P00030 | FUNDING ONLY ACTION | +$816,785 | NETWORK ENGINEERING SUPPORT SERVICES |
| July 26, 2021 | P00029 | EXERCISE AN OPTION | +$626,372 | NETWORK ENGINEERING SUPPORT SERVICES |
| December 17, 2020 | P00028 | FUNDING ONLY ACTION | −$5,567 | NETWORK ENGINEERING SUPPORT SERVICES |
| November 16, 2020 | P00027 | OTHER ADMINISTRATIVE ACTION | no money | NETWORK ENGINEERING SUPPORT SERVICES |
| September 28, 2020 | P00026 | FUNDING ONLY ACTION | +$1,595,479 | NETWORK ENGINEERING SUPPORT SERVICES |
| August 24, 2020 | P00025 | OTHER ADMINISTRATIVE ACTION | no money | NETWORK ENGINEERING SUPPORT |
| July 29, 2020 | P00024 | EXERCISE AN OPTION | +$598,305 | NETWORK ENGINEERING SUPPORT SERVICES |
| July 7, 2020 | P00023 | EXERCISE AN OPTION | +$182,435 | NETWORK ENGINEERING SUPPORT SERVICES |
| April 24, 2020 | P00022 | FUNDING ONLY ACTION | +$585,460 | NETWORK ENGINEERING |
| March 31, 2020 | P00021 | FUNDING ONLY ACTION | +$194,361 | NETWORK ENGINEERING |
| February 20, 2020 | P00020 | FUNDING ONLY ACTION | +$194,837 | NETWORK ENGINEERING |
| January 23, 2020 | P00019 | FUNDING ONLY ACTION | +$194,361 | NETWORK ENGINEERING |
| December 23, 2019 | P00018 | FUNDING ONLY ACTION | +$194,837 | NETWORK ENGINEERING |
| October 23, 2019 | P00017 | OTHER ADMINISTRATIVE ACTION | no money | NETWORK ENGINEERING SUPPORT |
| October 10, 2019 | P00016 | FUNDING ONLY ACTION | −$106,452 | DE-OBLIGATE CLINS 0004, 0005, AND 0006 |
| July 30, 2019 | P00015 | EXERCISE AN OPTION | +$974,183 | TASKS 1-4 |
| March 4, 2019 | P00014 | FUNDING ONLY ACTION | −$23,318 | DE-OBLIGATION-NETWORK ENGINEERING SUPPORT |
| December 13, 2018 | P00013 | OTHER ADMINISTRATIVE ACTION | no money | ADDING GOVERNMENT FURNISHED PROPERTY AND APPLICABLE CLAUSES. |
| September 19, 2018 | P00012 | FUNDING ONLY ACTION | +$1,844,631 | TASK 4 SECURE MOBILITY/UNIFIED O&M SUPPO |
| July 30, 2018 | P00011 | EXERCISE AN OPTION | +$368,926 | EXERCISE OPTION YEAR ONE (1) |
| April 30, 2018 | P00010 | FUNDING ONLY ACTION | +$368,020 | IGF::OT::IGF TASK 3 NETWORK ENGINEERING SUPPORT SER |
| April 3, 2018 | P00009 | EXERCISE AN OPTION | +$94,390 | WITHIN SCOPE INCREASED - TASK 4 |
| March 14, 2018 | P00008 | FUNDING ONLY ACTION | +$154,352 | INCREMENTAL FUNDING IGF::OT::IGF |
| February 26, 2018 | P00007 | FUNDING ONLY ACTION | +$154,567 | INCREMENTAL FUNDING FOR WHCA NETWORK ENGINEERING CONTRACT |
| January 19, 2018 | P00006 | FUNDING ONLY ACTION | +$212,825 | ADDED FUNDING |
| December 29, 2017 | P00005 | FUNDING ONLY ACTION | +$96,309 | TASK 3 NETWORK ENGINEERING SUPPORT SER IGF::OT::IGF |
| November 28, 2017 | P00004 | CHANGE ORDER | no money | IGF::CT::IGF ADDED DFARS CLAUSES |
| September 12, 2017 | P00003 | FUNDING ONLY ACTION | +$309,134 | IGF::CT::IGF INCREMENTAL FUNDING |
| September 5, 2017 | P00002 | FUNDING ONLY ACTION | no money | IGF::CT::IGF REALIGNMENT OF FUND |
| August 17, 2017 | P00001 | FUNDING ONLY ACTION | +$155,069 | IGF::CT::IGF WHCA NETWORK ENGINEERING (NE), OPERATIONS AND MAINTENANCE (O&M) SUPPORT SERVICES FUNDING MODIFICATION |
| June 30, 2017 | base | not on file | +$310,138 | IGF::CT::IGF TASK 3 NETWORK ENGINEERING SUPPORT SER |
Last refreshed November 4, 2026 at 2:31 PM UTC.