GENERAL DYNAMICS INFORMATION TECHNOLOGY, INC.

Federal contract award, General Dynamics Information Technology, $36,214,995

Key CONT_AWD_N6339423C0009_9700_-NONE-_-NONE-. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 114 days before this system saw it. One version on record.

Cite this row

On this site https://evidence.ourrevolution.media/filings/general-dynamics-information-technology/CONT_AWD_N6339423C0009_9700_-NONE-_-NONE-
At the source https://www.usaspending.gov/award/CONT_AWD_N6339423C0009_9700_-NONE-_-NONE-
Observed 2026-09-05, version 1, retrieved 2026-09-05T01:08:57Z
Content hash 54c408e8ebd94b997d68e137c79fcb798189d36f252c09eafcf37a5e1aa59230

The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.

Versions

VersionAmountChangeOccurredPublishedRetrievedHow it arrivedContent hash
1
current
$36,214,995first versionSeptember 29, 2023May 14, 20262026-09-05T01:08:57Zhistorical sweep54c408e8ebd9

Archived copy

None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.

What the amount is made of

76 recorded actions, so the amount is the award's current total across all of them. 43 of them obligated money. Measured 2026-09-15, when USAspending reported a total obligation of $36,214,995.

Action dateModificationTypeObligatedDescription as recorded
May 14, 2026P00037FUNDING ONLY ACTION+$165,500ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 14, 2026P00037FUNDING ONLY ACTION+$4,880,200ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 5, 2026P00036SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 5, 2026P00036SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 29, 2026P00035OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 29, 2026P00035OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 7, 2026P00034FUNDING ONLY ACTION+$250,106ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 7, 2026P00034FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 23, 2026P00033FUNDING ONLY ACTION+$539,629ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 23, 2026P00033FUNDING ONLY ACTION+$644,668ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 6, 2026P00032FUNDING ONLY ACTION+$614,222ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 6, 2026P00032FUNDING ONLY ACTION+$625,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
January 30, 2026P00031FUNDING ONLY ACTION+$362,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
January 30, 2026P00031FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
December 15, 2025P00030SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
December 15, 2025P00030SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$1,064,945ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
October 20, 2025P00029FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
October 20, 2025P00029FUNDING ONLY ACTION+$200,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 30, 2025P00028SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 30, 2025P00028SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 25, 2025P00027EXERCISE AN OPTION+$3,568,577ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 25, 2025P00027EXERCISE AN OPTION+$856,270ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 17, 2025P00026OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 17, 2025P00026OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 8, 2025P00025FUNDING ONLY ACTION+$44,450ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 8, 2025P00025FUNDING ONLY ACTION+$333,492ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 3, 2025P00024FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 3, 2025P00024FUNDING ONLY ACTION+$863,962ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
July 10, 2025P00023FUNDING ONLY ACTION+$673,710ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
July 10, 2025P00023FUNDING ONLY ACTION+$270,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
June 23, 2025P00022SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
June 23, 2025P00022SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$228,996ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 8, 2025P00021SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$89,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 8, 2025P00021SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$1,200,216ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 14, 2025P00020SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$187,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 14, 2025P00020SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$185,578ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 26, 2025P00019SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
March 26, 2025P00019SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
February 28, 2025P00018SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$295,455ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
February 28, 2025P00018SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$20,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
December 23, 2024P00017FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
December 23, 2024P00017FUNDING ONLY ACTION+$1,000,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
November 21, 2024P00016OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
November 21, 2024P00016OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
November 12, 2024P00015FUNDING ONLY ACTION+$521,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
November 12, 2024P00015FUNDING ONLY ACTION+$1,287,153ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 30, 2024P00014FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 30, 2024P00014FUNDING ONLY ACTION+$889,810ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 27, 2024P00013EXERCISE AN OPTION+$2,583,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 27, 2024P00013EXERCISE AN OPTION+$1,480,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 20, 2024P00012OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 20, 2024P00012OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 10, 2024P00011FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
September 10, 2024P00011FUNDING ONLY ACTION+$667,765ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
August 5, 2024P00010OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
August 5, 2024P00010OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
July 3, 2024P00009OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
July 3, 2024P00009OTHER ADMINISTRATIVE ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
June 21, 2024P00008FUNDING ONLY ACTION+$2,417,638ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
June 21, 2024P00008FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 30, 2024P00007FUNDING ONLY ACTION+$300,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 30, 2024P00007FUNDING ONLY ACTIONno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 14, 2024P00006SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
May 14, 2024P00006SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPEno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK 41 VERTICAL LAUNCHING SYSTEM.
April 18, 2024P00005FUNDING ONLY ACTION+$1,000,000MK 41 VLS ISEA SUPPORT, INCREMENTAL FUNDING.
April 18, 2024P00005FUNDING ONLY ACTIONno moneyMK 41 VLS ISEA SUPPORT, INCREMENTAL FUNDING.
March 15, 2024P00004FUNDING ONLY ACTION+$310,100ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK41 VERTICAL LAUNCHING SYSTEM.
March 15, 2024P00004FUNDING ONLY ACTION+$400,000ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MK41 VERTICAL LAUNCHING SYSTEM.
February 2, 2024P00003FUNDING ONLY ACTION+$1,180,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
February 2, 2024P00003FUNDING ONLY ACTION+$932,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
December 13, 2023P00002FUNDING ONLY ACTION+$1,370,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
December 13, 2023P00002FUNDING ONLY ACTION+$200,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
November 29, 2023P00001SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$300,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
November 29, 2023P00001SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE+$600,000MK 41 VERTICAL LAUNCHING SYSTEM ENGINEERING SERVICES
September 29, 2023basenot on fileno moneyENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MARK 41 VERTICAL LAUNCHING SYSTEM
September 29, 2023basenot on file+$613,554ENGINEERING SERVICES TO UPGRADE, INSPECT, TEST, AND DELIVER COMPONENTS OF THE MARK 41 VERTICAL LAUNCHING SYSTEM

Last refreshed November 4, 2026 at 2:31 PM UTC.