LEIDOS, INC.
Federal contract award, Leidos, $15,215,410
Key CONT_AWD_70T04018F5DAP4039_7013_HSTS0415DCT4056_7013. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 351 days before this system saw it. One version on record.
Cite this row
70b810fb5d6ef28642cd194502815e38c73cd82362d743e47cdd09f13342551eThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $15,215,410 | first version | June 27, 2018 | September 19, 2025 | 2026-09-05T00:54:56Z | historical sweep | 70b810fb5d6e |
Archived copy
https://web.archive.org/web/20261012174229/https://www.usaspending.gov/award/CONT_AWD_70T04018F5DAP4039_7013_HSTS0415DCT4056_7013 captured by this system, October 12, 2026
What the amount is made of
18 recorded actions, so the amount is the award's current total across all of them. 7 of them obligated money. Measured 2026-10-12, when USAspending reported a total obligation of $15,215,410.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| September 19, 2025 | P00017 | OTHER ADMINISTRATIVE ACTION | −$179,827 | THIS MODIFICATION IS BEING PROCESSED TO REMOVE UNBILLED CANCELLING FUNDS FROM THE AWARD IN ACCORDANCE TO TSA YEAR END PROCEDURES. |
| September 10, 2024 | P00016 | OTHER ADMINISTRATIVE ACTION | −$106,478 | THIS MODIFICATION IS BEING PROCESSED TO REMOVE UNBILLED CANCELLING FUNDS FROM THE AWARD IN ACCORDANCE TO TSA YEAR END PROCEDURES. |
| April 13, 2022 | P00015 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL SCOPE FOR IAD, SEE SECTION 3.2.4 FOR THE DETAILS OF THE MODIFICATION. THIS WORK WILL BE DONE WITHIN THE EXISTING FUNDING ON THE TASK ORDER. |
| January 25, 2022 | P00014 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE THROUGH JULY 31, 2022. |
| December 3, 2021 | P00013 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF MODIFICATION P00013 IS TO EXTEND THE POP THROUGH JANUARY 30, 2022 AT NO COST TO THE GOVERNMENT. |
| June 10, 2021 | P00012 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF MODIFICATION P00010 IS TO EXTEND THE POP THROUGH APRIL 30, 2021, AND TO UTILIZE EXISTING FUNDS TO COMPLETE WORK ON 8 EXISTING AND 6 NEW AIRPORT SITES AT NO COST TO THE GOVERNMENT. |
| April 30, 2021 | P00011 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$6,214,143 | THE PURPOSE OF MODIFICATION P00011 IS TO EXTEND THE POP THROUGH DECEMBER 31,2021, AND ADD ADDITIONAL SCOPE. |
| December 18, 2020 | P00010 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF MODIFICATION P00010 IS TO EXTEND THE POP THROUGH APRIL 30, 2021, AND TO UTILIZE EXISTING FUNDS TO COMPLETE WORK ON 8 EXISTING AND 6 NEW AIRPORT SITES AT NO COST TO THE GOVERNMENT. |
| December 4, 2020 | P00009 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF MODIFICATION P00009 IS TO EXTEND THE PERIOD OF PERFORMANCE FROM DECEMBER 4, 2020 TO DECEMBER 31, 2020 AT NO COST. |
| July 23, 2020 | P00008 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF MODIFICATION P00008 IS TO EXTEND THE PERIOD OF PERFORMANCE FROM AUGUST 3, 2020 TO DECEMBER 4, 2020. ALL CONTRACT DELIVERABLES (CDRLS) ARE PUT ON HOLD FROM AUGUST 3, 2020 UNTIL A NEW MODIFICATION IS DONE. |
| April 16, 2020 | P00007 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF MODIFICATION P00007 IS TO EXTEND THE PERIOD OF PERFORMANCE FROM MAY 3, 2020 TO AUGUST 3, 2020. |
| December 20, 2019 | P00006 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF MODIFICATION P00006 IS TO EXTEND THE PERIOD OF PERFORMANCE BY 4 MONTHS AND ADJUST THE SCOPE FOR IAD AND FLL. |
| August 2, 2019 | P00004 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$3,474,390 | THE PURPOSE OF MODIFICATION P00004 IS TO EXECUTE SITE REMEDIATION AT MIA, FLL, RDU FOR THE INSTALLATION OF THE CREDENTIAL AUTHENTICATION TECHNOLOGY UNITS. THIS MODIFICATION WILL ALSO EXTEND THE PERIOD OF PERFORMANCE TO 3 JANUARY 2020. |
| July 2, 2019 | P00005 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF MODIFICATION P00005 IS TO UPDATE THE SOW TO REFLECT CHANGES AT BOS. |
| March 27, 2019 | P00003 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF THIS MODIFICATION IS TO 1) REMOVE THE PERIOD OF PERFORMANCE WITHIN THE CLIN DESCRIPTIONS FOR CLIN 00001A, 00002A, 00004A, AND 00007A AND 2) REALIGN FUNDING FROM CLINS 00007A IN THE AMOUNT OF $218,541.92 TO NEWLY ESTABLISHED CLIN 00001C IN THE AMOUNT OF $218,541.92 FOR A TOTAL AMOUNT OF $218,541.92, IN SUPPORT OF CONTINUED "PROGRAM MANAGEMENT (CAT X REMEDIATION)" SUPPORT THROUGH AUGUST 3, 2019 AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| September 24, 2018 | P00002 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,486,298 | THE PURPOSE OF THIS MODIFICATION IS TO EXECUTE THE REMEDIATION OF THE FOLLOWING PILOT AND CAT X SITES: ATL, BOS, BWI, CLT, DCA AND IAD FOR THE INSTALLATION OF THE CREDENTIAL AUTHENTICATION TECHNOLOGY (CAT) UNITS. |
| August 16, 2018 | P00001 | EXERCISE AN OPTION | +$1,553,603 | THE PURPOSE OF THIS MODIFICATION IS TO COMPLETE SITE SURVEYS AT CAT III AND IV AIRPORTS IN THE EAST REGION TO IDENTIFY INFRASTRUCTURE NEEDED TO OPERATE CAT, CT, AND ASL TECHNOLOGY. |
| June 27, 2018 | base | not on file | +$2,773,280 | THE PURPOSE OF THIS TASK ORDER IS TO COMPLETE A SITE SURVEY AT CAT X,I,II, III AND IV AIRPORTS IN THE EAST REGION, IN AN EFFORT TO IDENTIFY THE EXISTING AND NECESSARY ELECTRICAL AND DATA INFRASTRUCTURE NEEDED TO OPERATE THE CREDENTIAL AUTHENTICATION TECHNOLOGY (CAT), COMPUTED TOMOGRAPHY (CT) X-RAY SCANNING AND AUTOMATED SCREENING LANE (ASL) TECHNOLOGY, AT THE DESIGNATED LOCATIONS. |