LEIDOS, INC.
Federal contract award, Leidos, $64,993,374
Key CONT_AWD_FA865019C1941_9700_-NONE-_-NONE-. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 138 days before this system saw it. One version on record.
Cite this row
c9028718ab6d948a2db02669515b5e9b1dad65881940b5749d0769c44e16acc0The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $64,993,374 | first version | July 2, 2019 | April 20, 2026 | 2026-09-05T00:54:30Z | historical sweep | c9028718ab6d |
Archived copy
https://web.archive.org/web/20261010214225/https://www.usaspending.gov/award/CONT_AWD_FA865019C1941_9700_-NONE-_-NONE- captured by this system, October 10, 2026
What the amount is made of
61 recorded actions, so the amount is the award's current total across all of them. 56 of them obligated money. Measured 2026-10-13, when USAspending reported a total obligation of $64,993,374.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| July 1, 2026 | P00061 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| April 20, 2026 | P00060 | FUNDING ONLY ACTION | +$595,867 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| April 7, 2026 | P00059 | OTHER ADMINISTRATIVE ACTION | no money | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| March 3, 2026 | P00057 | FUNDING ONLY ACTION | +$2,715,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| February 12, 2026 | P00056 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| August 22, 2025 | P00055 | FUNDING ONLY ACTION | +$200,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| July 31, 2025 | P00054 | FUNDING ONLY ACTION | +$2,755,788 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| June 16, 2025 | P00053 | FUNDING ONLY ACTION | +$650,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| May 5, 2025 | P00052 | FUNDING ONLY ACTION | +$1,605,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| April 29, 2025 | P00051 | FUNDING ONLY ACTION | +$300,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| February 21, 2025 | P00050 | FUNDING ONLY ACTION | +$268,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| February 5, 2025 | P00049 | FUNDING ONLY ACTION | +$842,065 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| November 20, 2024 | P00048 | FUNDING ONLY ACTION | +$2,461,827 | RAPID TECHNOLOGY DEVOLOPMENT AND DEMONSTRATIONS |
| September 23, 2024 | P00047 | FUNDING ONLY ACTION | +$9,463 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| September 18, 2024 | P00046 | FUNDING ONLY ACTION | +$1,792,583 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| July 17, 2024 | P00045 | FUNDING ONLY ACTION | +$53,600 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| July 2, 2024 | P00044 | FUNDING ONLY ACTION | +$3,383,635 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| May 31, 2024 | P00043 | FUNDING ONLY ACTION | +$2,570,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| April 22, 2024 | P00042 | FUNDING ONLY ACTION | +$1,517,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| April 10, 2024 | P00041 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$180,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| February 8, 2024 | P00040 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,894,888 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| October 23, 2023 | P00039 | FUNDING ONLY ACTION | +$500,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| September 25, 2023 | P00038 | FUNDING ONLY ACTION | +$253,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| August 28, 2023 | P00037 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$3,127,493 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| July 13, 2023 | P00036 | FUNDING ONLY ACTION | +$944,108 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| June 6, 2023 | P00035 | FUNDING ONLY ACTION | +$695,848 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| May 3, 2023 | P00034 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,492,113 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| April 3, 2023 | P00033 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,565,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| February 23, 2023 | P00032 | FUNDING ONLY ACTION | +$271,369 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| January 20, 2023 | P00031 | FUNDING ONLY ACTION | +$1,990,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| November 30, 2022 | P00030 | FUNDING ONLY ACTION | +$276,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| September 23, 2022 | P00029 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,890,602 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| August 15, 2022 | P00028 | FUNDING ONLY ACTION | +$500,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| July 7, 2022 | P00027 | FUNDING ONLY ACTION | +$1,295,505 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| June 10, 2022 | P00026 | FUNDING ONLY ACTION | −$564,187 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| May 13, 2022 | P00025 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| May 4, 2022 | P00024 | FUNDING ONLY ACTION | +$200,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| April 8, 2022 | P00023 | FUNDING ONLY ACTION | +$200,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEPLOYMENT |
| April 4, 2022 | P00022 | FUNDING ONLY ACTION | +$985,149 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| January 6, 2022 | P00021 | FUNDING ONLY ACTION | +$450,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| December 3, 2021 | P00020 | FUNDING ONLY ACTION | +$150,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| November 23, 2021 | P00019 | FUNDING ONLY ACTION | +$508,253 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| October 28, 2021 | P00018 | FUNDING ONLY ACTION | +$630,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| September 16, 2021 | P00017 | FUNDING ONLY ACTION | +$3,201,062 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION |
| August 26, 2021 | P00016 | FUNDING ONLY ACTION | +$4,851,208 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| August 20, 2021 | P00015 | FUNDING ONLY ACTION | +$2,245,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS |
| July 28, 2021 | P00014 | FUNDING ONLY ACTION | +$159,177 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| June 11, 2021 | P00013 | FUNDING ONLY ACTION | +$772,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| May 4, 2021 | P00012 | FUNDING ONLY ACTION | +$2,231,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| March 8, 2021 | P00011 | OTHER ADMINISTRATIVE ACTION | +$1,075,843 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| November 5, 2020 | P00010 | FUNDING ONLY ACTION | +$522,229 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| September 18, 2020 | P00009 | FUNDING ONLY ACTION | +$5,041 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| September 9, 2020 | P00008 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$3,350,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| July 27, 2020 | P00007 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$522,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTARTIONS (RTD2) |
| June 10, 2020 | P00006 | FUNDING ONLY ACTION | +$65,225 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTARTIONS (RTD2) |
| April 21, 2020 | P00005 | FUNDING ONLY ACTION | +$797,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| March 18, 2020 | P00004 | FUNDING ONLY ACTION | +$182,400 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| January 14, 2020 | P00003 | FUNDING ONLY ACTION | +$50,000 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATION (RTD2) |
| November 5, 2019 | P00002 | FUNDING ONLY ACTION | +$2,263,170 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
| August 2, 2019 | P00001 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTARTIONS (RTD2) |
| July 2, 2019 | base | not on file | +$546,050 | RAPID TECHNOLOGY DEVELOPMENT AND DEMONSTRATIONS (RTD2) |
Last refreshed November 4, 2026 at 2:31 PM UTC.