LEIDOS BIOMEDICAL RESEARCH INC

Federal contract award, Leidos, $7,158,692

Key CONT_AWD_HHSN26100052_7529_HHSN261201500003I_7529. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 365 days before this system saw it. One version on record.

Cite this row

On this site https://evidence.ourrevolution.media/filings/leidos/CONT_AWD_HHSN26100052_7529_HHSN261201500003I_7529
At the source https://www.usaspending.gov/award/CONT_AWD_HHSN26100052_7529_HHSN261201500003I_7529
Observed 2026-09-05, version 1, retrieved 2026-09-05T00:55:14Z
Content hash 1f1e518c8582cdbe8524fbcf468ed235c2abf5e08b27d24b4d62a02651a9d75b

The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.

Versions

VersionAmountChangeOccurredPublishedRetrievedHow it arrivedContent hash
1
current
$7,158,692first versionSeptember 15, 2017September 5, 20252026-09-05T00:55:14Zhistorical sweep1f1e518c8582

Archived copy

https://web.archive.org/web/20261013175411/https://www.usaspending.gov/award/CONT_AWD_HHSN26100052_7529_HHSN261201500003I_7529 captured by this system, October 13, 2026

What the amount is made of

8 recorded actions, so the amount is the award's current total across all of them. 5 of them obligated money. Measured 2026-10-11, when USAspending reported a total obligation of $7,158,692.

Action dateModificationTypeObligatedDescription as recorded
September 5, 2025P00007OTHER ADMINISTRATIVE ACTION+$24,579B539 REFURBISHMENT & INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1 MOD 007 - ADD FY20 FUNDING
July 30, 2020P00006OTHER ADMINISTRATIVE ACTION+$16,440B539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
May 29, 2020P00005OTHER ADMINISTRATIVE ACTIONno moneyB539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
November 21, 2019P00004OTHER ADMINISTRATIVE ACTION+$421,974B539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
September 26, 2019P00003OTHER ADMINISTRATIVE ACTIONno moneyB539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
July 11, 2019P00002OTHER ADMINISTRATIVE ACTIONno moneyIGF::OT::IGF B539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
April 27, 20181CHANGE ORDER+$773,548IGF::OT::IGF B539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1
September 15, 2017basenot on file+$5,922,151IGF::OT::IGF B539 REFURBISHMENT&INFRASTRUCTURE UPGRADES TO B539/1ST FLOOR, PHASE 1