| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $17,833,778 | first version | November 26, 2019 | August 28, 2025 | 2026-09-05T00:54:53Z | historical sweep | 9d8d4d628ce8 |
Archived copy
https://web.archive.org/web/20261012024932/https://www.usaspending.gov/award/CONT_AWD_HR001120C0019_9700_-NONE-_-NONE- captured by this system, October 12, 2026
What the amount is made of
21 recorded actions, so the amount is the award's current total across all of them. 18 of them obligated money. Measured 2026-10-12, when USAspending reported a total obligation of $17,833,778.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| August 28, 2025 | P00020 | OTHER ADMINISTRATIVE ACTION | −$185,022 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| June 18, 2024 | P00019 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| May 23, 2024 | P00018 | FUNDING ONLY ACTION | +$272,675 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| May 7, 2024 | P00017 | FUNDING ONLY ACTION | +$254,234 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| March 29, 2024 | P00016 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| March 4, 2024 | P00015 | FUNDING ONLY ACTION | +$350,000 | MARITIME MATERIALS TECHNOLOGY (M2T) PHASE 4 |
| November 9, 2023 | P00014 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | MARITIME MATERIALS TECHNOLOGY (M2T) |
| August 8, 2023 | P00013 | FUNDING ONLY ACTION | +$239,495 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM - FUNDING & PARTIAL STOP WORK ORDER |
| March 16, 2023 | P00012 | FUNDING ONLY ACTION | +$2,934,010 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| January 20, 2023 | P00011 | FUNDING ONLY ACTION | +$1,325,576 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| June 28, 2022 | P00010 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,746,048 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM |
| May 25, 2022 | P00009 | FUNDING ONLY ACTION | +$1,572,750 | MARITIME MATERIALS TECHNOLOGY (M2T) PHASE 3 PROGRAM |
| January 20, 2022 | P00008 | FUNDING ONLY ACTION | +$965,199 | MARITIME MATERIALS TECHNOLOGIES (M2T) INCREMENTAL FUNDING |
| December 1, 2021 | P00007 | EXERCISE AN OPTION | +$1,343,093 | MARITIME TECHNOLOGIES PROGRAM PHASE 3 EO14042 |
| March 3, 2021 | P00006 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,492,895 | MARITIME TECHNOLOGIES PROGRAM (M2T PHASE 2) |
| November 18, 2020 | P00005 | EXERCISE AN OPTION | +$969,235 | MARITIME TECHNOLOGIES PROGRAM (M2T, PHASE 2 |
| September 4, 2020 | P00004 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$194,335 | MARITIME MATERIALS TECHNOLOGIES (M2T) PROGRAM. |
| February 24, 2020 | P00003 | FUNDING ONLY ACTION | +$219,643 | MARITIME MATERIALS TECHNOLOGIES (M2T). |
| January 27, 2020 | P00002 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,003,455 | MARITIME MATERIALS TECHNOLOGIES |
| December 11, 2019 | P00001 | FUNDING ONLY ACTION | +$284,039 | MARITIME MATERIALS TECHNOLOGIES (M2T) |
| November 26, 2019 | base | not on file | +$852,118 | MARITIME MATERIALS TECHNOLOGIES (M2T) |