LEIDOS, INC.
Federal contract award, Leidos, $116,882,445
Key CONT_AWD_N0001919C0051_9700_-NONE-_-NONE-. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 347 days before this system saw it. One version on record.
Cite this row
90a8932ad9a8209030576b2e9b9a7f05d36b8a17ee2a421f9b720fd15b4f655aThe source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $116,882,445 | first version | February 25, 2019 | September 23, 2025 | 2026-09-05T00:54:23Z | historical sweep | 90a8932ad9a8 |
Archived copy
None on file. An archived copy is optional corroboration and never a condition of this filing’s provenance, which is the stored response and its hash above; see the methodology page.
What the amount is made of
25 recorded actions, so the amount is the award's current total across all of them. 19 of them obligated money. Measured 2026-10-13, when USAspending reported a total obligation of $105,674,223.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| June 9, 2026 | P00024 | OTHER ADMINISTRATIVE ACTION | −$11,208,221 | DE-OBLIGATION OF REMAINING FUNDS PRIOR TO CLOSEOUT. |
| September 23, 2025 | P00023 | FUNDING ONLY ACTION | +$3,061,918 | CLIN 0006 INCREMENTAL FUNDING |
| September 2, 2025 | P00022 | CHANGE ORDER | +$9,349,290 | SRD CHANGE ORDER |
| April 29, 2025 | P00021 | FUNDING ONLY ACTION | +$4,814,395 | COST OVERRUN |
| February 19, 2025 | P00020 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$2,196,397 | ARC TRAINING MATERIAL |
| November 22, 2024 | P00019 | FUNDING ONLY ACTION | +$2,113,648 | INCREMENTAL FUNDING CLIN 0006 |
| September 26, 2024 | P00018 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE OF LINE ITEM 0008 THROUGH 30 AUGUST 2024, INCLUSIVE OF CONSIDERATION, AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| May 14, 2024 | P00017 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE DELIVERY DATE OF CLIN 0008 AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| February 6, 2024 | P00016 | FUNDING ONLY ACTION | +$8,880,404 | ARC INCREMENTAL FUNDING MOD |
| December 6, 2023 | P00015 | OTHER ADMINISTRATIVE ACTION | +$1,394,686 | INCREMENTAL FUNDING |
| June 16, 2023 | P00014 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$8,000,000 | CLIN 0006 OVERRUN FUNDING |
| May 25, 2023 | P00013 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | ARC MAINLINE RB2 SOW UDPATE |
| January 31, 2023 | P00012 | OTHER ADMINISTRATIVE ACTION | no money | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE STATEMENT OF WORK. |
| December 20, 2022 | P00011 | OTHER ADMINISTRATIVE ACTION | +$10,323,482 | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CLIN 0006. |
| May 16, 2022 | P00010 | OTHER ADMINISTRATIVE ACTION | +$12,854,592 | IN ACCORDANCE WITH NAVAIR PID #N00019-22-NORFP-TPM272-0022, THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CLIN 0006 AND TO UPDATE THE DELIVERY DATE FOR CLIN 0008. THERE SHALL BE NO CHANGE IN PRICE AS A RESULT OF THIS MODIFICATION. |
| March 23, 2022 | P00009 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$484,366 | CONTRACT MODIFICATION UNDER N0001919C0051 IN SUPPORT OF ALQ 214 FA 18 ADAPTIVE RADAR COUNTERMEASURES THREAT RADAR MODEL DEVELOPMENT PROCUREMENT. THIS MODIFICATION SUPPORTS THE DESIGN, DEVELOPMENT, AND INTEGRATION OF A THREAT RADAR MODEL INTO EXISTING STIMULATORS AT THE ELECTRONIC COMBAT STIMULATION BRANCH FOR OPEN AND CLOSE LOOP EW TESTING WITH FA 18. |
| November 30, 2021 | P00008 | FUNDING ONLY ACTION | +$10,271,926 | INCREMENTAL FUNDING |
| September 9, 2021 | P00007 | FUNDING ONLY ACTION | +$1,250,000 | ADD FUNDING TO CLIN 0006 |
| April 23, 2021 | P00006 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$3,831,999 | ADDITIONAL HIL STATION |
| March 10, 2021 | P00005 | FUNDING ONLY ACTION | +$11,250,033 | FUNDING AND CDRL MOD |
| August 27, 2020 | P00004 | ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | +$13,894,969 | ARC MAINLINE INTEGRATION |
| May 6, 2020 | P00003 | FUNDING ONLY ACTION | +$1,350,000 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SOW AND EXTEND POP TO 30 SEP 2020. |
| December 16, 2019 | P00002 | OTHER ADMINISTRATIVE ACTION | no money | CDRL MODIFICATION |
| April 1, 2019 | P00001 | OTHER ADMINISTRATIVE ACTION | no money | ADMIN MOD. |
| February 25, 2019 | base | not on file | +$11,560,339 | NRE |