LEIDOS, INC.
Federal contract award, Leidos, $15,337,169
Key CONT_AWD_W900KK22F0017_9700_W900KK22D0004_9700. First seen by this system September 5, 2026 through the historical sweep, new to the watchlist, public 157 days before this system saw it. One version on record.
Cite this row
8f15f042e3d80fd354baa2afbe542947b44629beada9b47102c5d52e4b1f5d64The source record can change after this date; the key, hash and retrieval time name exactly the response this system stored. See license and citation.
Versions
| Version | Amount | Change | Occurred | Published | Retrieved | How it arrived | Content hash |
|---|---|---|---|---|---|---|---|
| 1 current | $15,337,169 | first version | January 28, 2022 | April 1, 2026 | 2026-09-05T00:54:56Z | historical sweep | 8f15f042e3d8 |
Archived copy
https://web.archive.org/web/20261012174059/https://www.usaspending.gov/award/CONT_AWD_W900KK22F0017_9700_W900KK22D0004_9700 captured by this system, October 12, 2026
What the amount is made of
19 recorded actions, so the amount is the award's current total across all of them. 11 of them obligated money. Measured 2026-10-12, when USAspending reported a total obligation of $15,337,169.
| Action date | Modification | Type | Obligated | Description as recorded |
|---|---|---|---|---|
| July 1, 2026 | P00018 | OTHER ADMINISTRATIVE ACTION | no money | DO2 GUNNERY TRAINING SYSTEMS (GTS) - BRADLEY COUNTER-DRONE ENHANCEMENT (BCDE) IMPLEMENTATION OF THE NEW BADGER ROUND INTO THE BRADLEY COFT WITH A FIRM FIXED PRICE OF $560,709 |
| April 1, 2026 | P00017 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$560,709 | DO2 GUNNERY TRAINING SYSTEMS (GTS) - BRADLEY COUNTER-DRONE ENHANCEMENT (BCDE) IMPLEMENTATION OF THE NEW BADGER ROUND INTO THE BRADLEY COFT WITH A FIRM FIXED PRICE OF $560,709 |
| December 31, 2025 | P00016 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$920,460 | GUNNERY TRAINER SYSTEMS - BRADLEY GUNNER TRAINER |
| September 26, 2025 | P00015 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$1,529,106 | BRADLEY GUNNERY MANUAL UPDATES FOR DELIVERY ORDER (DO), W900KK-22-F-0017. |
| March 28, 2025 | P00014 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | EXTEND PERIOD OF PERFORMANCE (POP) FOR CONTRACT LINE ITEM NUMBERS (CLINS) 0007 AND 0010 TO 30 SEPTEMBER 2025. |
| December 19, 2024 | P00013 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | TECH REFRESH NRE & UPGRADE KITS (M/I) |
| August 21, 2024 | P00012 | CHANGE ORDER | no money | TECH REFRESH NRE & UPGRADE KITS (M/I) |
| May 1, 2024 | P00011 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | MODIFICATION TO INCORPORATE DD254 AS AN ATTACHMENT UNDER SECTION J. |
| April 4, 2024 | P00010 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | TECH REFRESH NRE & UPGRADE KITS (M/I) |
| December 6, 2023 | P00009 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | TECH REFRESH NRE & UPGRADE KITS (M/I) |
| August 11, 2023 | P00008 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$373,682 | MODIFICATION TO CHANGE DELIVERY SCHEDULES AND QUANTITIES |
| July 26, 2023 | P00007 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | −$320,880 | MODIFICATION TO DE-OBLIGATE FUNDING AND VALUE FROM MULTIPLE CLINS AS A RESULT OF AN ECP CHANGING DELIVERY LOCATIONS. |
| March 22, 2023 | P00006 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$2,093,824 | PRODUCTION, TESTING, DELIVERY, AND INSTALLATION OF TECH REFRESHES/CONCURRENCY UPGRADES TO EXISTING BRADLEY CONDUCT OF FIRE TRAINERS. MODIFICATION IS FOR EXERCISE OF PRE-DETERMINED PRICES. |
| December 1, 2022 | P00005 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$99,478 | PRODUCTION, TESTING, DELIVERY AND INSTALLATION OF TECH REFRESHES TO EXISTING SYSTEMS AND CONCURRENCY UPGRADES TO THE BRADLEY CONDUCT OF FIRE TRAINER. MODIFICATION IS RESTORE FUNDING REMOVED ON P00004. |
| November 28, 2022 | P00004 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | −$99,478 | PRODUCTION, TESTING, DELIVERY AND INSTALLATION OF TECH REFRESHES TO EXISTING SYSTEMS AND CONCURRENCY UPGRADES TO THE BRADLEY CONDUCT OF FIRE TRAINER. MODIFICATION IS TO UPDATE SOW TO INCORPORATE CYBERSECURITY AND GTLF TRAINING EXERCISES. |
| August 29, 2022 | P00003 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | no money | PRODUCTION, TESTING, DELIVERY AND INSTALLATION OF TECH REFRESHES TO EXISTING SYSTEMS AND CONCURRENCY UPGRADES TO THE BRADLEY CONDUCT OF FIRE TRAINER. MODIFICATION IS ADMINISTRATIVE TO UPDATE THE SOW/PBP SCHEDULE/CONTRACTING OFFICER. |
| June 9, 2022 | P00002 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | +$425,953 | GUNNERY TRAINING SYSTEMS. BRADLEY TECH REFRESH NRE & UPGRADE KITS (M/I). |
| May 25, 2022 | P00001 | OTHER ADMINISTRATIVE ACTION | −$425,953 | PRODUCTION, TESTING, DELIVERY AND INSTALLATION OF TECH REFRESHES TO EXISTING SYSTEMS AND CONCURRENCY UPGRADES TO THE BRADLEY CONDUCT OF FIRE TRAINER. MODIFICATION IS ADMINISTRATIVE TO ADDRESS ITEMS FROM POST-AWARD CONFERENCE AND REALIGN FUNDS. |
| January 28, 2022 | base | not on file | +$10,180,268 | PRODUCTION, TESTING, DELIVERY AND INSTALLATION OF TECH REFRESHES TO EXISTING SYSTEMS AND CONCURRENCY UPGRADES TO THE BRADLEY CONDUCT OF FIRE TRAINER |
Last refreshed November 4, 2026 at 2:31 PM UTC.